Nepal Starts $49.94 Million Push to Drain Four Dangerous Glacial Lakes

13 Min Read
Nepal Starts $49.94 Million Push to Drain Four Dangerous Glacial Lakes

Four lakes, three metres each, and a deadline in 2033

Nepal has begun a $49.94 million programme to take water out of four Himalayan lakes before the loose rock and ice holding them back gives way. The GLOF Sanjibani project, run with the United Nations Development Programme, was launched at an inception workshop in Kathmandu on November 25, 2026 (one account placed the workshop a day earlier) and runs until 2033, with the Green Climate Fund recording an estimated completion date of 12 March 2033.

Contents
  1. Four lakes, three metres each, and a deadline in 2033
  2. Who pays, and who keeps paying after 2033
  3. Two months after the rivers came down
  4. A cryosphere changing faster than the paperwork
  5. What lowering a lake can and cannot do
  6. Warnings that have to arrive in minutes
  7. Provinces, mayors and power companies
  8. Fifteen lakes and 40 years of arithmetic
  9. What is still open
  10. Key Points

The engineering target is precise. Water levels at Dona lake in Manang, Lower Barun in Sankhuwasabha and Lumding Tsho in Solukhumbu will each come down by three metres. Hongu 2, also in Solukhumbu, will drop by one metre. The Manang lake appears as Thulagi in the fund's approval papers, the name glaciologists use for the lake below the Thulagi glacier.

A glacial lake sits behind a dam of loose rock, sand and ice debris left by a retreating glacier. When that dam is overtopped, or when an avalanche of ice and rock drops into the water, the lake can empty in a surge that carries boulders, trees and sediment down a valley within minutes. Removing part of the water lowers what such a surge can release.

The Centre of Hydrology and Water Resources Research, under the Ministry of Energy, Water Resources and Irrigation, leads implementation, with the Department of Chure and Watershed Conservation, the Department of National Parks and Wildlife Conservation and the National Disaster Risk Reduction and Management Authority as partners. UNDP counts more than 385,000 direct beneficiaries, 55 per cent of them women, and nearly two million more people in downstream basins as indirect beneficiaries. The fund's project record gives 2.4 million people expected to gain resilience.

Four other pieces sit alongside the lake works: climate risk information built into planning, more hydrological and meteorological monitoring, early warning systems, and protective infrastructure downstream. Those works include more than 150 hectares of reforestation, check dams (low barriers across gullies that slow water and trap sediment) and walls of wire baskets packed with stone and planted with vegetation, known as vegetative gabion walls.

The name carries its own message. Deepak KC, UNDP's lead technical expert and coordinator for the project, said Sanjibani was chosen because lowering the four lakes is expected to protect the lives of millions of people.

Advertisement

Who pays, and who keeps paying after 2033

The money comes from four places. The Green Climate Fund approved a grant of $36,158,230, or about $36.16 million. Nepal's government adds $11.32 million, UNDP $2.14 million and private partners $320,000, taking cofinancing to $13.78 million and the total to $49.94 million.

The fund's board cleared the grant in July 2025 at a meeting in Port Moresby, Papua New Guinea, and a first tranche has already reached UNDP, according to Bapon Fakhruddin of the fund's secretariat. The arrangement reaches past the seven year implementation window: after 2033 the government takes over operation and maintenance for a further seven years.

Kamal Ram Joshi, director general of the Department of Hydrology and Meteorology at the Ministry of Energy, Water Resources and Irrigation, presented the project as a continuation of work already done at two other lakes.

Following the successful interventions in Tsho Rolpa and Imja Glacial Lakes, the Department of Hydrology and Meteorology (DHM), in partnership with UNDP, national institutions, and local stakeholders, is advancing a major initiative to reduce the risk of glacial lake outburst floods (GLOF) in the Koshi and Gandaki river basins.

Henry Gonzalez, chief investment officer of the Green Climate Fund, tied the timing to the pace of ice loss across the mountain range.

With Himalayan glaciers retreating at an accelerating rate, immediate measures are critical for mountain communities' resilience.

Amrit Lamsal, joint secretary at the Ministry of Finance and Nepal's designated authority to the fund, put the arithmetic of responsibility plainly: Nepal produces less than 0.1 per cent of global greenhouse gas emissions and still carries consequences it did not create. He said the project links risk reduction to national development priorities and accountability frameworks.

Advertisement

Two months after the rivers came down

Floods on August 26, 2026 killed more than 1,400 people, left more than 5,000 others missing, including foreign nationals, and washed away several settlements along the Bhotekoshi and Trishuli river corridors. Public and private infrastructure across those valleys was badly damaged, including hydropower plants and roads.

Kyoko Yokosuka, UNDP's resident representative in Nepal, drew the link between that disaster and the new project in her remarks at the launch.

The devastating floods we witnessed just two months ago in the Rasuwa-Bhotekoshi and Gandaki basin reminded us how quickly climate-related extreme hazards can become humanitarian and economic disasters. They also reinforce a simple but important message: we cannot wait for the next disaster to take action.

The bill from that disaster is far larger than the adaptation budget. Reconstruction needs have been put at about $4.7 billion by Avishek Shrestha, adviser to the minister for agriculture, forests and environment, while Nepal has identified $20 million for recovery work through the Fund for Responding to Loss and Damage plus $1.6 million for operational costs, as it made its COP31 appeal for mountain specific finance. Against those figures, $49.94 million buys work at four lakes and warning systems in four river basins.

Advertisement

A cryosphere changing faster than the paperwork

Sanjiv Baral, executive director of the Centre of Hydrology and Water Resources Research, brought the case for speed with numbers. Glaciers across the Hindu Kush Himalaya retreated 65 per cent faster between 2011 and 2020 than in the previous decade, he said, and the Thulagi glacier in Manang is losing about 30 metres of length a year.

More than 30 glacial lake outburst events have been recorded in Nepal and surrounding areas over the past six decades, around 15 of them in Nepal and 11 in Tibet. The 2016 Bhote Koshi outburst, Baral said, caused an estimated $112 million in economic losses from a lake covering only about 0.017 square kilometres.

A 2020 study by UNDP and the International Centre for Integrated Mountain Development identified 47 lakes with a high potential to cause damage in Nepal, including 21 inside the country, 25 in Tibet and one in India. Forty two of them sit in the Koshi basin, nine in the Dudh Koshi basin alone. The Green Climate Fund puts Nepal's lake count above 2,000, of which 21 are considered potentially dangerous.

One measurement points the other way. Baral said the total area of Nepal's glacial lakes fell by around 23 per cent between 1987 and 2017 even as individual lakes grew, while Deepak KC of UNDP said the total area covered by the country's glacial lakes rose by 25 per cent over the same 30 years. Both men agree on the consequence: retreating ice and expanding lakes are putting more water above more people.

Nepal's neighbours are counting the same problem. Bhutan mapped 620 glacial lakes in its latest inventory, up from 567 in 2021, and flagged 17 as potentially dangerous, with nine of them in a single sub-basin, according to the 620 lakes count published by the National Centre for Hydrology and Meteorology.

Advertisement

What lowering a lake can and cannot do

Evidence from across the border sets a limit on what the four lakes can deliver. A 2022 study in Natural Hazards and Earth System Sciences modelled worst case outbursts in the Poiqu basin, which drains into Nepal, including at Jialongco, where engineering work had already cut the lake level by an average of 16 metres and stabilised the dam area. The lowering had minimal effect on the size or arrival time of a worst case flood set off by a large ice avalanche.

Those floods would reach Nyalam within 6 to 11 minutes of the chain of events starting and Zhangmu, near the Nepal border, in about 30 minutes, the authors found. Their conclusion was that hard engineering at the lake alone can prove insufficient, because it leaves the exposure and vulnerability downstream untouched, and that the 2022 modelling study supports early warning, land use zoning matched to what a valley can tolerate and programmes to build local response capacity.

The project design reflects part of that lesson. Lake lowering is paired with monitoring and warning systems rather than presented as a substitute for them, and the protective works downstream are aimed at the exposure the Poiqu research describes.

Advertisement

Warnings that have to arrive in minutes

Early warning coverage under the project extends to vulnerable stretches of the Marsyangdi, Arun, Dudhkoshi and Lower Barun river basins. Stations, communications links and data from hydropower projects along those corridors could feed the system, suggested Nabin Raj Singh, secretary at the Water and Energy Commission Secretariat, rather than being built twice.

Getting a message to a household in the path of a flood is a separate problem from detecting the flood. Nepal tested one route in November 2026, when engineers at a Nepal Telecom tower in Balambu sent a message that reached 40 to 50 selected phones within five to 10 seconds during a cell broadcast test watched by two ministers. Cell broadcast pushes one alert to every compatible handset in a defined area, without phone numbers or an internet connection, which matters when a surge can reach a settlement in minutes.

Dharma Raj Uprety, chief executive of the National Disaster Risk Reduction and Management Authority, described the kind of coordination the warning chain needs.

It is essential to launch common initiatives by the government, development partners, private sectors and local community for building resilience.

Dr Dharmaraj Upreti, who holds the same post in a second account of the launch, said strengthening warning systems means making sure science based information reaches communities well before a hazard arrives. Dr Rajan Bhattarai, deputy executive director and spokesperson of the Centre for Hydrology and Water Resources Research, confirmed the fund grant of $36.16 million within the $49.94 million total.

Advertisement

Provinces, mayors and power companies

Most of the land under threat is administered far from Kathmandu. Indra Prasad Sapkota, secretary of the Koshi provincial government, asked for provincial and local governments to sit inside the project's decisions and its delivery.

The Koshi Province Government is pleased that the Koshi Basin has been given priority under the project and is ready to cooperate.

Sapkota asked that the province's 10 identified priority programmes be folded into the work, with budgets extended to the local level, since provincial and local governments are the closest tiers of government when a climate disaster strikes and when its aftermath is managed.

Dhan Bahadur Gurung, chairperson of Naso Rural Municipality in Manang, one of the target local governments, said he expects the initiative to support safer settlements and better livelihoods through land use planning based on evidence, detailed research and participation by residents.

Private money enters through two doors. The project is partnering with hydropower companies and the tourism sector to cofinance hydro-meteorological stations and warning systems, and will work with private actors and local governments on community based adaptation. The Independent Power Producers' Association, Nepal and the Nepal Tourism Board are named as key partners, alongside the Ministry of Finance.

Singh said the project would adopt integrated and collaborative methods, and that the government intends to develop the Centre of Hydrology and Water Resources Research into a centre of excellence that can carry the work past the funding cycle.

Advertisement

Fifteen lakes and 40 years of arithmetic

The four lakes are a fraction of the list. Singh set out the pace problem in a single comparison at the launch.

If it takes seven to 10 years to manage four glacial lakes, it could take at least another 30 to 40 years to manage the remaining 15. All development partners should work together to complete the management of high-risk glacial lakes within the next seven to 10 years.

Sanjiv Baral made the same point with a shorter image, calling glacial lakes ticking time bombs because the mountains are changing rapidly and a small breach can cause losses of billions of dollars. He said lowering work must be done urgently, with proper safety precautions and in line with environmental and social safeguards, a point he repeated at the launch workshop.

Bapon Fakhruddin of the Green Climate Fund secretariat argued the project should lay the ground for money to move beyond its four basins.

We are currently supporting only four river basins, but another 21 glacial lakes and glacier-related areas are at high risk.

He said science and technology should be used to draw in other development partners and financial institutions so support can reach the remaining high risk areas. Nepal's record shows what each intervention costs in time: Tsho Rolpa in Dolakha district was dealt with in 2000 and Imja lake in Solukhumbu in 2016, which is two lakes in about 16 years.

Advertisement

What is still open

No schedule for the lake lowering work has been published, and neither has the volume of water each lake will release. Designs described so far are preliminary, with the three metre and one metre figures the only publicly given measurements. The project record lists it as under implementation, with completion estimated for 12 March 2033, and the government's seven further years of operation and maintenance running past that.

Two other questions sit with the people who will live with the result. Whether warning systems reach every settlement in the four basins, and whether provincial and local budgets arrive alongside the federal money, will be settled as the work moves from the workshop stage into construction.

Key Points

  • Nepal and UNDP launched the GLOF Sanjibani project, worth $49.94 million, at an inception workshop in Kathmandu in late November 2026.
  • Water levels will fall by three metres each at Dona (Thulagi) in Manang, Lower Barun in Sankhuwasabha and Lumding Tsho in Solukhumbu, and by one metre at Hongu 2.
  • The Green Climate Fund provides a $36.16 million grant, Nepal $11.32 million, UNDP $2.14 million and private partners $320,000.
  • The Centre of Hydrology and Water Resources Research implements the project, which runs to 2033, with the government operating and maintaining it for seven years afterwards.
  • More than 385,000 people benefit directly, 55 per cent of them women, with about two million more protected indirectly downstream; the fund records 2.4 million people gaining resilience.
  • Works include more than 150 hectares of reforestation, check dams, gabion walls and warning systems in the Marsyangdi, Arun, Dudhkoshi and Lower Barun basins.
  • Floods on August 26, 2026 killed more than 1,400 people and left more than 5,000 missing along the Bhotekoshi and Trishuli corridors.
  • Hindu Kush Himalaya glaciers retreated 65 per cent faster between 2011 and 2020 than in the previous decade, and the Thulagi glacier is losing about 30 metres a year.
  • A 2020 UNDP and ICIMOD study found 47 lakes with high damage potential, 21 of them in Nepal, leaving 15 to 17 beyond the current programme.