Big investment promises meet a test of local benefits
Malaysia expects 27 data centre projects worth an estimated RM225.97 billion to create 4,053 jobs, including 3,523 skilled positions, as the government presses investors to deliver more Malaysian employment, supplier contracts and technology transfers.
Contents
- Big investment promises meet a test of local benefits
- Where the projects stand
- Who is expected to get the skilled jobs?
- How the wages compare
- Why RM225.97 billion becomes spending over time
- Economic activity is already appearing in national figures
- Electricity and water put conditions on expansion
- Closer scrutiny of operations and imported chips
- More digital services require more protection
- Key Points
Deputy Digital Minister Datuk Wilson Ugak Kumbong told the Dewan Rakyat on November 18, 2026, that new projects approved under the Data Centre Task Force (DCTF) must meet a minimum 30% local content requirement. The Malaysian Investment Development Authority (MIDA) monitors compliance through implementation reports submitted every six months.
The employment forecast, based on the position in the second quarter of 2026, puts skilled roles at about 87% of the expected total. Those jobs cover electrical and mechanical engineering, networking, cybersecurity, and the operation and maintenance of facilities that house computers and run digital services.
Wilson described the government's priorities during parliamentary questions about how much economic value Malaysia receives from the industry's large investment commitments:
The government's priority is to ensure these investments translate into highly skilled job opportunities, greater participation by local companies, technology development and sustainable economic value for the country,
The debate now extends well beyond attracting investors. Parliament has also examined wages, tax receipts, business opportunities in surrounding districts, pressure on water and electricity supplies, and the growing need to protect digital infrastructure from cyberattacks.
Malaysia's challenge is to turn expensive buildings and computing equipment into lasting income and skills for residents, while making operators responsible for the infrastructure their facilities require.
Where the projects stand
The DCTF, established in February 2025 and jointly chaired by the Digital Ministry and the Investment, Trade and Industry Ministry, approved 27 projects with estimated investment of RM225.97 billion by October 2026.
A Digital Ministry written parliamentary answer published on October 14 gave a more detailed geographical breakdown using figures through July 2026. Of those 27 projects, 16 were in Johor, 10 in Selangor and one in Negeri Sembilan. One was operating and 26 were under construction at that point.
Johor therefore accounted for nearly 60% of the DCTF projects. The concentration makes the availability of engineers, contractors, electricity and water particularly important in the state.
The wider national pipeline is larger. Wilson's November statement put the number of approved projects at 117 through October 2026, although another account of his remarks placed the same total in the first half of the year. Approved investment in data centres and cloud computing reached RM95.8 billion in the first half.
A November 17 account put investment across the 117 projects at RM385.7 billion, with 55 operating, 19 under construction, 16 awaiting construction and 27 at other implementation stages. The DCTF figures cover a subset of this national pipeline.
The main milestones show how quickly approvals have been followed by questions about delivery:
- February 2025: The DCTF was established.
- July 2026: Its 27 projects formed part of 84 approved projects nationally.
- October 2026: The national total reached 117 approved projects, according to Wilson's November statement.
- November 12: Investment Minister Datuk Seri Johari Abdul Ghani outlined plans for legal requirements covering operating information.
- November 18: Parliament examined employment, local suppliers, wages and economic returns.
Who is expected to get the skilled jobs?
The Digital Ministry expects Malaysians to fill 89.21% of the 3,523 skilled positions in the DCTF projects. That works out to approximately 3,143 jobs for Malaysian workers.
Electrical engineers help keep power systems reliable. Mechanical engineers maintain equipment such as cooling systems. Networking staff keep computers connected, while cybersecurity teams protect systems and information. Operations and maintenance workers keep the facilities running continuously.
TalentCorp Malaysia is developing a Data Centre Facilities Management Programme to train local participants in operations and maintenance. The government is also working with operators, industry bodies and training institutions to expand industrial training, knowledge transfer and professional certification.
Wilson said the industry creates fewer direct jobs than sectors such as manufacturing, but its positions tend to require more specialised skills. Construction, engineering and support services provide further employment outside the facilities themselves, although no total for these indirect jobs was given.
The wider construction opportunity is illustrated by Google's planned Malaysia expansion, announced on November 4. The company expects its US$15 billion investment during 2027 and 2028, including three new data centres, to support more than 37,000 local jobs annually during construction. That forecast covers a wider network of businesses and a different development programme from the DCTF employment estimate.
How the wages compare
Wilson cited Bank Negara Malaysia's report for the third quarter of 2025 when describing pay in the industry. Positions at entry level offered approximately RM3,000 to RM7,000 a month, while senior roles offered RM10,000 to RM30,000.
Malaysia's median monthly salary in 2024 was RM2,793. The median is the middle figure in a pay distribution: half of workers earn more and half earn less.
At RM3,000, the bottom of the data centre entry range was RM207, or about 7.4%, above that national benchmark. RM7,000 was roughly 2.5 times the median, while the senior range was approximately 3.6 to 10.7 times as high.
The comparison shows why access to training matters. The higher salaries are attached to particular technical responsibilities, so local recruitment depends on workers gaining the qualifications and practical experience those roles require.
Why RM225.97 billion becomes spending over time
Data centres require large initial investments in servers, electrical equipment, cooling systems and energy infrastructure. Much of the equipment is imported, and capital spending takes place in stages as projects are developed.
A project can therefore move through approval, construction, equipment installation and operation over an extended period. Local construction contracts may arrive before permanent operating jobs, while purchases of imported servers send part of the expenditure overseas.
Datuk Seri Dr Wee Jeck Seng, the MP for Tanjung Piai, asked the government about actual economic returns from employment, skilled wages, tax revenue and Malaysian vendor participation. He also sought opportunities for talent development and businesses in nearby Pontian and Tanjung Piai.
The 30% local content condition is intended to secure a Malaysian share of activity in areas including engineering, maintenance, networking and technology solutions. Operators are also encouraged to develop domestic suppliers and transfer technology.
MIDA's reports every six months provide a recurring check on implementation. For local companies, the practical opportunity lies in winning contracts and building the ability to supply technical services throughout a facility's operating life, rather than only during construction.
Economic activity is already appearing in national figures
The Department of Statistics Malaysia reported economic growth of 5.5% in the third quarter of 2026 compared with a year earlier. Data centre construction was among the activities it identified as supporting growth.
Construction outside the residential sector rose 16.7%, while information and communication activity grew 8.7%. Manufacturing of electrical, electronic and optical products increased 16.5%.
Gross fixed capital formation, which measures investment in productive assets such as buildings and machinery, rose 8.1%. Purchases of machinery and equipment increased 12.7%, while investment in structures rose 5.5%.
These figures show several channels through which the industry contributes: building facilities, buying equipment and supplying digital services. Malaysia's economy grew 5.6% during the first nine months of 2026, compared with 4.8% in the same period of 2025.
Government revenue also arrives through several channels. Wilson said direct corporate income tax receipts should increase gradually after investment incentives expire for some projects. Development and operation already generate sales and service tax, local authority assessment taxes and revenue associated with utilities.
Electricity and water put conditions on expansion
Dr Halimah Ali, the MP for Kapar, raised concerns about the cumulative effects of a proposed industrial park covering 656.8 hectares in Bukit Kerayong, expected to include a data centre campus. She asked about flooding, water and electricity supplies, roads and drainage.
Wilson said applications are assessed for water and electricity availability, infrastructure capacity and energy efficiency before approval. Operators are encouraged to use renewable energy and more efficient technology.
The government has also approved a 30% renewable energy minimum for data centres, with the Energy Commission developing the framework. As of August 2026, facilities had contracted for 2,346 megawatts of electricity but were using 1,374 megawatts, leaving 972 megawatts reserved but unused.
On November 12, Johari said operators would be billed for unused electricity capacity they had requested. Reserving capacity requires the utility to keep it available, even when a facility is using less during its early stages.
That policy connects project development to costs outside the data centre boundary. Electricity networks must be ready to supply the promised capacity, while neighbouring communities and businesses also depend on reliable power and water.
Closer scrutiny of operations and imported chips
Johari said requirements to submit operating information, including electricity use and the number of imported graphics processing units (GPUs), would be placed in law. The government also wants information about operators, major technology companies using each facility and their locations.
GPUs are chips that perform many calculations at once. They are widely used to train and run artificial intelligence systems, making them valuable equipment for data centres serving AI customers.
The Digital Ministry is examining whether existing laws can be used to act against the reexport of GPUs subject to United States restrictions. Johari said some businesses had rented data centre space and imported chips, then sent the chips onward to other countries instead of using them locally.
No legislative timetable was given for the operating information requirements. The review of existing legal powers over GPU reexports was also still under way.
More digital services require more protection
National Cyber Security Agency chief executive Dr Megat Zuhairy Megat Tajuddin warned that expanding digital infrastructure increases the number of systems and connections that require protection. In cybersecurity, this is called the attack surface: the possible entry points that attackers can try to exploit.
Megat Zuhairy explained the connection between more infrastructure and the work needed to secure it:
Therefore, the more digital infrastructure is developed, the wider the attack surface that needs to be monitored and protected to safeguard the country's digital ecosystem,
Malaysia recorded more than 5,000 cyber incidents through September 2026. Annual incidents had already risen from 3,076 in 2024 to 5,837 in 2025, an increase of approximately 90%.
Megat Zuhairy said increasingly sophisticated AI tools could give cybercriminals greater ability to launch attacks. The Cyber Security Act 2024 strengthens preparedness among organisations covered by the National Critical Information Infrastructure framework, which concerns systems essential to the country.
Cybersecurity is therefore both a recruitment need and an operating responsibility for the expanding industry. Wilson said the government wants data centre investment to support Malaysia's AI and cybersecurity ecosystem in line with its AI Nation 2030 ambition.
Key Points
- Twenty seven DCTF projects worth an estimated RM225.97 billion are expected to create 4,053 jobs, including 3,523 skilled positions.
- Malaysians are expected to fill 89.21% of those skilled jobs, approximately 3,143 positions.
- New DCTF projects must meet a minimum 30% local content requirement, monitored through company reports every six months.
- Entry salaries range from RM3,000 to RM7,000 monthly, while senior positions offer RM10,000 to RM30,000, according to figures Wilson cited.
- The national pipeline contains 117 approved projects, with 55 operating in the November figures.
- Government oversight is expanding to electricity reservations, operating information, imported GPUs and cybersecurity preparedness.