Thailand to Open Rama 3 Link to M82 Without Tolls on December 25, 2026

11 Min Read
Thailand to Open Rama 3 Link to M82 Without Tolls on December 25, 2026

Two agencies, two opening dates and two toll schedules

Motorists travelling from Bangkok toward Thailand's southern provinces will gain another expressway connection on December 25, 2026. The Expressway Authority of Thailand (EXAT) will begin a trial of the part of the Rama 3–Dao Khanong–Western Outer Ring expressway that runs above Rama II Road, creating a connection with the M82 motorway. The EXAT section will be free to use until September 2027. A toll will be considered after that period, but no rate has been selected.

Contents
  1. Two agencies, two opening dates and two toll schedules
  2. What the M82 trial allows drivers to do
  3. Toll dates and the journey farther south
  4. How a difficult construction programme reached 97.28 percent
  5. Safety and dust remained central concerns
  6. Two projects worth 31.559 billion baht move toward cabinet review
  7. Why the Double Deck plan includes a fare decision before construction
  8. The next opening dates run from 2027 to 2032
  9. Easy Pass changes will reach beyond the new roads
  10. At a Glance

Construction of the complete Rama 3 project had reached 97.28 percent when EXAT governor Surapong Laophulsuk outlined the agency's plans at its 54th anniversary. Deputy Prime Minister and Transport Minister Phiphat Ratchakitprakarn confirmed the December opening on November 27 while presenting a broader programme that includes new expressways in Bangkok and Phuket.

August 28, 2026 was a separate milestone. At 10am that Friday, the Department of Highways opened the full 25 km M82 elevated motorway between Bang Khun Thian, Ekachai and Ban Phaeo for a trial without tolls. December 25 therefore concerns the EXAT connection to a motorway that is already carrying trial traffic. The agencies also have different commercial schedules: EXAT expects to charge for its section after the free period, while the Department of Highways is targeting commercial tolling on the M82 in 2029.

What the M82 trial allows drivers to do

Department of Highways director general Piyapong Jiwattanakulpaisarn said the M82 opening followed Phiphat's instruction to accelerate the project and make journeys from Bangkok to the southern provinces faster and more convenient. Civil construction was 98 percent complete, allowing the department to add the 16.4 km section between Ekachai and Ban Phaeo to the free service and keep the route open around the clock.

Drivers can travel from the Southern Kanchanapisek Outer Ring Road onto the elevated motorway at the Bang Khun Thian interchange, continue above Rama II Road past Ekachai and finish at Ban Phaeo in Samut Sakhon. The route provides an alternative to the congested ground road while remaining construction is completed.

Entry and exit points at Phanthai Norasing, Mahachai 1, Mahachai 2 and Ban Phaeo have been operating since August 28. The Samut Sakhon 1 and Samut Sakhon 2 ramps are still under construction, and no opening dates have been given for them. The department expects to finish the remaining civil work by the end of 2026.

Safety rules apply because the civil work and safety systems are not yet complete. Cars are limited to 80 km/h, while trucks and buses must stay at or below 65 km/h. Pedestrians, bicycles, motorcycles of every engine size, vehicles with three wheels and pushcarts are prohibited on the elevated motorway. Those road users can continue using Rama II Road at ground level.

Advertisement

Toll dates and the journey farther south

Installation of the M82 toll collection and traffic control systems is scheduled to begin in 2027 and take about two years. The department aims to begin full commercial tolling in 2029. An earlier Transport Ministry schedule called for private investors to be selected for the system work during 2025 or 2026, with installation finishing in 2028 and tolls waived while that work proceeded.

Ban Phaeo gives drivers a continuing route south on Highway 35, also known as Rama II Road, toward Samut Songkhram. Traffic can then reach the Wang Manao interchange in Pak Tho district, Ratchaburi, and connect with roads serving other southern provinces. The department expects the elevated route to support freight, trade, manufacturing and tourism in Samut Sakhon, Samut Songkhram, Ratchaburi, Phetchaburi, Prachuap Khiri Khan and surrounding areas. No estimate of the number of minutes saved on a typical journey accompanied the opening plan.

Advertisement

How a difficult construction programme reached 97.28 percent

Rama II Road has carried years of construction alongside heavy traffic. An early 2025 update placed the Rama 3–Dao Khanong–Western Outer Ring project at 87.06 percent completion, with completion then scheduled for November of that year. The subsequent figure of 97.28 percent represents an increase of 10.22 percentage points, although the December 2026 trial still covers only the portion above Rama II Road.

January 2025 figures show how uneven progress had been across the project's five contracts. Contract 1 stood at 81.70 percent, Contract 2 at 94.72 percent and Contract 3 at 83.78 percent. Contract 4 was finished and operating, while Contract 5 had reached only 2.69 percent. Suriya Juangroongruangkit, who was transport minister at the time, described the contracts as ahead of schedule and said manpower and equipment were being increased. He hoped the route would open to the public during 2025.

The M82 also had sharply different progress figures along its two main sections in early 2025. The three contracts between Bang Khun Thian and Ekachai were 98.42 percent complete, while the ten contracts between Ekachai and Ban Phaeo stood at 70.60 percent. Highways Department chief Apirat Chaiwongnoi scheduled the Bang Khun Thian interchange contracts for completion in February or March 2025. Contracts from Ekachai to Ban Phaeo were due between August and November 2025, with the Ban Phaeo work itself scheduled for November. Suriya's objective at that stage was to finish the three active Rama II projects by the end of 2025.

Advertisement

Safety and dust remained central concerns

Six workers died when a crane collapsed on the M82 in Samut Sakhon on November 29, 2024. The investigation committee tentatively attributed the accident to unsafe working practices, while continuing to interview witnesses. Its final findings were expected within a month of the early 2025 construction update. The committee's conclusion at that stage was preliminary.

Construction agencies also had to control dust along Highway 35. PM2.5 refers to airborne particles no wider than 2.5 micrometres, which are small enough to travel deep into the lungs. The Highways Department sent water trucks to spray roads and central reservations. When PM2.5 exceeded 50 micrograms per cubic metre, crews used water mist at high pressure to capture dust in the affected areas. Suriya instructed the department to monitor every construction contract closely while curbing those emissions.

Two projects worth 31.559 billion baht move toward cabinet review

Phiphat identified the Phuket expressway's first phase, from Kathu to Patong, as one of two projects being prepared for cabinet consideration. The 3.98 km route has an estimated cost of 16.757 billion baht. It is intended to address traffic congestion and support tourism in Phuket, where travel between the island's interior and its western beaches can become heavily congested.

The second project is the 6.67 km Chalong Rat–Eastern Outer Ring expressway, formerly known as N2, with a budget of 14.802 billion baht. Together, the two budgets total 31.559 billion baht. Both entered the process for submission to the cabinet in August 2026, and Phiphat expected them to begin advancing during 2027.

EXAT's working targets provide a longer view. The Chalong Rat–Eastern Outer Ring route is intended to receive cabinet approval in early 2027 and enter service in 2030. Phuket's first phase is targeted to open in 2032 alongside a second phase running through Muang Mai, Ko Kaeo and Kathu. No length or budget for that second Phuket phase was included in the anniversary plan.

Advertisement

Why the Double Deck plan includes a fare decision before construction

Bangkok's proposed Double Deck expressway would add a second level over approximately 17 km between Ngam Wong Wan and Rama IX. Its estimated cost exceeds 34 billion baht, more than the combined budgets of the Phuket first phase and the Chalong Rat–Eastern Outer Ring project. EXAT is targeting cabinet consideration in early 2027 and an opening in 2031.

The project is undergoing review through the process for investment partnerships between the state and private companies. Such arrangements set out how financing, construction and operation will be divided between the public authority and its private partner. Phiphat said the policy committee considering the project should provide clarity by the middle of 2027, a later point in the year than EXAT's target for cabinet consideration.

A separate fare proposal could affect motorists much earlier. A private participant has proposed charging 50 baht for travel throughout the corridor from Ngam Wong Wan to Rama IX. Phiphat said that, once the policy review is clear, the fare could be introduced immediately without waiting for the additional level to be built. The 50 baht charge remains a proposal tied to that decision, rather than an announced toll for every EXAT road.

Advertisement

The next opening dates run from 2027 to 2032

One project is already under construction. The Chalong Rat extension from Chatuchot to Lam Luk Ka had advanced 13.62 percent by the November 2026 announcement. EXAT expects that section to open in November 2028. Its schedule sits among several dates that apply to different roads, agencies and stages of approval:

  • December 25, 2026: EXAT opens the Rama II Road portion of the Rama 3 project for a trial connecting with the M82.
  • September 2027: The EXAT free period is scheduled to run until this month. No exact changeover date or subsequent toll has been announced.
  • 2027 and 2028: Installation of the M82 toll collection and traffic control systems is expected to take about two years.
  • November 2028: The Chalong Rat extension from Chatuchot to Lam Luk Ka is expected to open.
  • 2029: The Department of Highways targets commercial toll operations on the full M82.
  • 2030: EXAT targets the opening of the Chalong Rat–Eastern Outer Ring expressway.
  • 2031: The Double Deck expressway between Ngam Wong Wan and Rama IX is targeted to enter service.
  • 2032: Both phases of the Phuket expressway are targeted to open.

These dates do not remove the need for the remaining approvals. The Double Deck project and its fare proposal still depend on the investment review, while the Phuket and Chalong Rat–Eastern Outer Ring projects must complete the cabinet process before their construction programmes can proceed.

Easy Pass changes will reach beyond the new roads

April 2027 is the scheduled launch for Easy Pass Postpaid. Postpaid billing means that each journey can be charged to a credit or debit card after it is made, removing the need to load money into an Easy Pass balance in advance. EXAT intends the service to reduce payment steps for motorists. It is also developing the EXAT Portal application as its main digital service channel.

EXAT has introduced an Easy Pass Smart Vending Machine as a pilot service point. The machine combines applications for an Easy Pass card, balance top-ups, toll payments, account checks and reward point redemption. Users can also replace an Easy Pass onboard unit, the small vehicle device that communicates with toll equipment. Putting these services in one machine gives motorists an alternative to visiting a staffed service centre.

November 2026 also featured in EXAT's programme for testing autonomous vehicles on the Chalong Rat expressway. The planned traffic management system would exchange information between vehicles and road infrastructure, providing advance warnings of incidents and reducing accident risks. For drivers, the nearest practical changes remain the M82 restrictions now in force, the EXAT connection opening on December 25 and postpaid Easy Pass billing in April 2027.

Advertisement

At a Glance

  • EXAT will open the Rama II Road portion of its Rama 3 expressway project on December 25, 2026, with free use until September 2027.
  • Construction of that project has reached 97.28 percent, and its future toll rate has not been decided.
  • The Department of Highways separately opened the full 25 km M82 for a free trial on August 28, 2026.
  • M82 cars are limited to 80 km/h, trucks and buses to 65 km/h, and several vehicle types are banned from the elevated road.
  • Commercial M82 tolling is targeted for 2029 after system installation, while the Samut Sakhon 1 and 2 ramps still need completion.
  • The Phuket first phase and Chalong Rat–Eastern Outer Ring projects have budgets totalling 31.559 billion baht.
  • The proposed Double Deck expressway would cost more than 34 billion baht and could bring an earlier decision on a 50 baht corridor fare.
  • Easy Pass Postpaid is scheduled for April 2027, alongside new digital services and trials of smarter road technology.