A record award, with final confirmation still to come
Samsung SDI is set to supply 751 megawatts, or 62.9 percent, of the 1,194 megawatts selected in South Korea's third energy storage system central contract tender. The Ministry of Climate, Energy and Environment and the Korea Power Exchange announced the preferred bidders on November 26, 2026. Samsung SDI's allocation covers nine of the 14 project sites. Final confirmation is due on December 4, and the battery orders associated with the round have an estimated value of around 2 trillion won.
Contents
- A record award, with final confirmation still to come
- Where the batteries will go, and why those grids need them
- How the rankings changed across three rounds
- Why the cheapest battery did not automatically win
- What the central contract market actually buys
- Samsung SDI's safety pitch meets a capacity squeeze
- SK On turns a smaller share into more factory work
- What the orders mean for suppliers and the US business
- Deadlines, Jeju's longer contract option and round four
- Key Points
SK On secured the remaining 443 megawatts, or 37.1 percent, across five mainland sites. LG Energy Solution, the largest of the three Korean battery producers by manufacturing capacity, did not participate. Its absence left a contest between two suppliers after the earlier rounds had drawn aggressive price competition from all three. About 60 companies competed for the storage projects themselves.
The tender notice originally sought 1,100 megawatts on the mainland and 80 megawatts on Jeju Island, totaling 1,180 megawatts. Awards were permitted to reach 105 percent of that volume. The selected projects comprise 12 mainland sites totaling 1,115 megawatts and two Jeju sites totaling 79 megawatts. At a discharge duration of six hours, the announced volume corresponds to about 7.08 gigawatt-hours, while the slightly larger selection corresponds to 7,164 megawatt-hours, or 7.164 gigawatt-hours.
Where the batteries will go, and why those grids need them
Six projects are in South Jeolla, five in North Jeolla, one in South Chungcheong and two on Jeju. This concentration reflects the combination of abundant solar and wind generation and insufficient transmission capacity in the Honam region and Jeju. An energy storage system, or ESS, absorbs electricity when production exceeds immediate demand and returns it to the grid when consumption rises or renewable output falls.
Samsung SDI's seven mainland wins are 96 megawatts each, giving it 672 megawatts before its Jeju allocation. It worked with Korea East-West Power, Korea Midland Power, Korea Western Power, Aegis and Equis on sites including Yeongam, Muju, Sinan and Nonsan. Both projects at the Pyoseon substation on Jeju also selected Samsung SDI. One is a 40 megawatt project involving SK Eternix, and the other is a 39 megawatt project involving Korea East-West Power and Aegis. Those 79 megawatts bring Samsung SDI's total to 751.
SK On's five sites are Haenam, Soseong, Jeongju, Muju and Gangjin, with the Gangjin project accounting for 59 megawatts. Korea Giga Platform had initially teamed with LG Energy Solution but moved to SK On for the Haenam, Soseong, Jeongju and Muju projects. A consortium of Korea Midland Power and Saman added the Gangjin site. For local communities, the awards mean grid equipment and construction work must now be followed by permits, installation and years of operation and maintenance.
How the rankings changed across three rounds
The three full rounds have allocated 2,322 megawatts. Samsung SDI holds 1,380 megawatts, or 59.4 percent, commonly rounded to 60 percent. SK On has 727 megawatts, or 31.3 percent, and LG Energy Solution has 215 megawatts, or 9.3 percent. The third round alone represents 51.4 percent of all capacity awarded across the three rounds, and its 1,194 megawatts exceed the 1,128 megawatts combined total of the first two.
- 2023: LG Energy Solution swept the volume in the earlier pilot program on Jeju.
- 2025: The first full round offered 540 megawatts, comprising 500 on the mainland and 40 on Jeju, and was the first to include the mainland. The allocation used in the cumulative results was 563 megawatts, with Samsung SDI taking 427 megawatts, about 76 percent, and LG Energy Solution taking 136.
- February 2026: The second round allocated 565 megawatts. SK On won 284 megawatts, or 50.3 percent, Samsung SDI won 202, or 35.7 percent, and LG Energy Solution won 79.
- November 2026: The third round selected 1,194 megawatts, with Samsung SDI returning to the leading position and SK On taking the remainder.
SK On's falling percentage therefore conceals an increase in business. Its planned supply rose 56 percent, from 284 megawatts in February to 443 megawatts in the latest round, even as its share dropped from 50.3 percent to 37.1 percent. LG Energy Solution said it would concentrate on reliably delivering existing orders and building its competitiveness over the medium and long term. Its decision removed the largest producer from the third contest but did not erase the 215 megawatts it accumulated earlier.
Why the cheapest battery did not automatically win
Price supplied half of the evaluation score in the third process, with the other half devoted to factors such as safety, supply capability and contributions to the domestic economy. Fire and equipment safety carried 25 points, including 11 points for the inherent fire safety of the battery system. Evidence could cover battery chemistry, testing associated with UL 9540A, protection for battery racks, monitoring and diagnostics, cooling equipment, emergency shutdowns, backup power and maintenance records.
Bidders also had to identify the manufacturer and production origin for cells, modules, racks, cathode and anode materials, separators, electrolyte, the power conversion system and the battery and energy management systems. The rules did not require a completely Korean supply chain. They allowed evaluators to score domestic production, supply resilience, local economic contributions, employment, maintenance services, recycling plans and the experience of major shareholders.
The first two rounds had produced what industry participants described as damaging price competition, because all three battery manufacturers were pursuing the work and lower prices improved a bid's position. Samsung SDI's nickel-based cells generally cost more to produce than lithium iron phosphate alternatives, yet its first round pricing was assessed as coming close to those alternatives. Conditions changed in the third round: LG Energy Solution withdrew, the available volume approached the remaining production capacity of the other two suppliers, and lithium prices were higher than during round two. Industry observers consequently expect better pricing than in the earlier contests, although detailed award prices have not been published.
What the central contract market actually buys
The Korea Power Exchange administers the market under the 11th Basic Plan for Electricity Supply and Demand, which covers 2024 to 2038. Winning storage operators receive contracts lasting 15 years that provide fixed capacity revenue in exchange for standby grid support and compliance with performance requirements. Battery manufacturers compete to supply those operators rather than simply selling batteries without an operating obligation. The latest mainland procurement also requires equipment capable of establishing grid voltage and frequency, at least 383 full charging and discharging cycles each year and performance guarantees lasting 15 years.
Greenberg Traurig lawyers Joseph Kim and Jared Raleigh explained the preceding framework in a 2025 auction legal guide. Projects in that round had to exceed 10 megawatts, or 60 megawatt-hours, and remain below 100 megawatts, or 600 megawatt-hours. Mainland systems needed at least 383 annual cycles, compared with 395 on Jeju, and commercial operation was required by December 2026. Winners had six months to obtain a Generation Business License, one month after licensing to sign with the Korea Power Exchange, and an obligation to post a performance bond equal to 10 percent of the bid value.
Investment controls continue after selection. Changes in control require approval from the Central Contract Market Committee. Under the Electricity Business Act, an acquisition giving an investor effective control, generally at a threshold of 20 percent, also requires approval from the Ministry of Trade, Industry and Energy. Foreign investors acquiring 10 percent or more must make a report under the Foreign Investment Promotion Act.
The procurement pipeline extends beyond this award. The government plans to obtain 2.1 gigawatts on the mainland between 2026 and 2029 and 0.12 gigawatts on Jeju between 2026 and 2028. That supports a wider electricity plan targeting approximately 21.7 percent of generation from renewable sources by 2030, compared with less than 10 percent in 2020. Storage provides a way to use electricity whose production time does not match the time consumers need it.
Samsung SDI's safety pitch meets a capacity squeeze
Samsung SDI built its offer around domestic production at Ulsan, Korean materials and components, and prismatic cells enclosed in rigid aluminum cases. The cells include vents that release gas and technology intended to stop heat spreading between adjacent cells. Thermal runaway is the dangerous process in which an overheating cell generates more heat than it can release, potentially triggering a fire or affecting neighboring cells.
The Samsung Battery Box units for these projects will also include Samsung Battery Intelligence, diagnostic software using artificial intelligence. Samsung SDI developed it with operating data from approximately 1,400 ESS installations. The software examines battery condition, the installation environment and usage patterns to identify abnormal cells. The company says it can warn operators of danger signs at least three days before thermal runaway or another abnormal event. It also plans to expand the software's use in existing installations and use additional operating data to improve diagnosis.
Manufacturing capacity is the immediate constraint. At six hours, Samsung SDI's 751 megawatt allocation represents approximately 4.5 gigawatt-hours of batteries. The Ulsan plant has annual production capacity of about 15 gigawatt-hours, but only around 5 gigawatt-hours of NCA ESS capacity was estimated to remain available after earlier domestic awards and overseas orders were assigned to its lines. NCA refers to a nickel, cobalt and aluminum chemistry. The new domestic allocation would therefore occupy nearly all of that estimated spare capacity.
A Samsung SDI representative said the company was expanding production in Korea and abroad and could respond to orders by considering customer demand and improving line efficiency. The company has not disclosed the production start date for its planned ESS lithium iron phosphate line at Ulsan or the supply volume for each project. Industry checks indicate that a mother line has been established but full investment in the Ulsan production line has not begun. The start of domestic LFP output will influence how Samsung SDI approaches the fourth tender and later rounds.
SK On turns a smaller share into more factory work
SK On's 443 megawatts correspond to approximately 2.7 gigawatt-hours at six hours. Its Seosan plant in South Chungcheong has 7 gigawatt-hours of annual capacity, of which 3 gigawatt-hours are being converted from electric vehicle battery production to lithium iron phosphate, or LFP, batteries for storage. Equipment replacement and trial production are scheduled for completion by the end of 2026. The planned 3 gigawatt-hours can accommodate the latest 2.7 gigawatt-hour allocation without converting additional lines beyond that program.
An SK On representative connected the result to this Korean manufacturing base and the use of domestic materials.
Domestic production and the use of locally made key components helped us secure a substantial share of orders in the ESS central contract market.
The representative said the existing Seosan facilities could handle the secured orders. LFP cathode material is to come from L&F, while electrolytes and separators will also be sourced from Korean suppliers. Deliveries from the converted operation are targeted for 2027, with earlier program deliveries also beginning that year.
SK On's GRIDON storage system can be used in direct current blocks and in alternating current blocks that integrate a power conversion system, which changes battery electricity into a form suitable for the grid. Its safety equipment includes electrochemical impedance spectroscopy, a diagnostic method that examines internal resistance and battery reactions, and a cooling water fire suppression system controlled by dual valves. In October 2026, SK On passed a large fire test conducted by CSA Group and met evaluation items under the UL 9540A standard. The company said its design disperses heat over an extended period to prevent thermal runaway from spreading to cells in a neighboring container.
What the orders mean for suppliers and the US business
Domestic production gives Ulsan and Seosan a steadier workload at a time when slower electric vehicle demand has made factory utilization a concern for battery producers. The effect extends beyond cell assembly. Cathode material, electrolyte and separator suppliers gain opportunities because the tender rewards Korean industrial contributions. Both Samsung SDI and SK On said no further changes to their domestic investment plans had been confirmed following the awards.
North America provides a larger source of storage demand as technology companies invest in data centers for artificial intelligence. SK On is also converting lines at its Georgia plant to make LFP storage batteries. Those lines will support a 1 gigawatt-hour agreement signed with Flatiron Energy Development in September 2025 for a project in Massachusetts. A separate agreement announced in August 2026 calls for 9 gigawatt-hours of LFP pouch cells to be supplied to NeoVolta Power over five years beginning in 2027.
SK On has set a target of more than 20 gigawatt-hours of global ESS orders during 2026 and has discussed another 10 gigawatt-hours or more with potential US customers, although those discussions are not firm orders. Samsung SDI is also expanding its international storage business, including an arrangement to supply 16 gigawatt-hours of US-made LFP cells to Jupiter Power starting in 2029. The Korean awards give both manufacturers domestic production work while they pursue that larger overseas market.
Deadlines, Jeju's longer contract option and round four
The third process moved from bidder registration between September 28 and October 2 to proposals submitted from October 6 through November 4, followed by supporting data, business plans and evidence through November 11. Preferred bidders were then selected on November 26. Final volumes are due on December 4, 2026. Successful operators must obtain power generation business permits by August 2027 and complete construction by February 2029. Failure to obtain the required permit following the grid review can lead to forfeiture of an award.
Jeju also offered a contract option lasting 25 years, intended to make projects using storage technologies other than lithium more practical. Both Pyoseon projects ultimately went to bidders led by Samsung SDI on contracts lasting 15 years, so this round did not produce a selected project using a different storage chemistry under that option.
The government plans to open the fourth central contract market in the first half of 2027. Before then, operators must turn preferred status into final awards and permits, while the battery suppliers must align factory output with delivery schedules. Detailed bid prices and Samsung SDI's domestic LFP production timetable remain undisclosed.
Key Points
- Samsung SDI secured 751 megawatts, or 62.9 percent, across nine sites; SK On secured 443 megawatts, or 37.1 percent, across five.
- The 1,194 megawatt selection is Korea's largest ESS tender and exceeds the first two rounds combined total of 1,128 megawatts.
- At six hours, the selected projects represent 7.164 gigawatt-hours of storage, with associated battery orders estimated at around 2 trillion won.
- Cumulative awards across three rounds total 2,322 megawatts: Samsung SDI has 1,380, SK On 727 and LG Energy Solution 215.
- Price supplied half the score, while fire safety, domestic production and industrial contributions helped determine the winners.
- Final confirmation is due December 4, 2026, permits are required by August 2027, and construction must finish by February 2029.
- A fourth tender is planned for the first half of 2027, with factory capacity likely to shape the next contest.