A legal label for a busy corridor
Sri Lanka has formally classified the 5.729 km Port Access Elevated Expressway in Colombo as an expressway, giving the road a clearer legal status in the national network. Minister of Transport, Highways and Urban Development Bimal Niroshan Rathnayaka signed the order under Section 9(1)(a) of the National Thoroughfares Act, No. 40 of 2008. The special government gazette notification, Gazette Extraordinary No. 2516/02, was published on November 23, 2026.
Contents
- A legal label for a busy corridor
- What the gazette order says
- Where the elevated road runs
- Three interchanges, with one still unfinished
- How much time could drivers save?
- Timeline of the declaration and works
- Night closures at Ingurukade
- What changes for Colombo drivers
- What the port gains from direct access
- What is still not finished
- Why the legal classification matters
- Key Points
The decision arrives as construction begins on a link between the New Kelani Bridge and the elevated highway. Supun Abeywickrama, Project Director of the Port Access Elevated Highway Project, said the completed link could be travelled in about five to six minutes, compared with 40 minutes or more for drivers entering Colombo on Baseline Road during peak traffic hours.
An expressway is a road kept apart from ordinary street traffic. Drivers use ramps and interchanges rather than stopping at each junction, so vehicles can keep moving at higher speeds. The new classification places the Port Access road in that category under Sri Lanka's thoroughfares law, after it had already been named a national highway in an earlier gazette.
The order gives the road a legal class before all connections are finished. Public use depends on the completion and opening of the works, including ramp connections. The construction link and future extensions are separate pieces that will decide how drivers actually use the corridor. This sequence matters for a route serving both port traffic and city traffic.
What the gazette order says
The order was signed in Battaramulla and published as Gazette Extraordinary No. 2516/02 on November 23, 2026. It followed Gazette Extraordinary No. 2514/36 of November 13, 2026, which had declared the same stretch a national highway. The two notices, ten days apart, show the road being moved into the expressway class soon after its national highway designation.
The gazette places the expressway in the Colombo district of the Western Province. It says the road has an average width of 23.5 meters. It begins at the Kelanitissa Power Plant Junction, where drivers can connect with the Kelanitissa System Interchange near the Colombo-Katunayake Expressway and Colombo-Kandy Road, and ends near Chaithya Road.
The main elevated structure is a viaduct 5,132 meters long, built with two lanes and separate carriageways over Colombo Port land and internal port roads. A viaduct is like a bridge that carries a road above the ground, and a dual carriageway separates traffic moving in opposite directions. That design allows the highway to pass over port roads instead of forcing vehicles to weave through them at street level.
The declaration covers the whole corridor. The schedule focuses on the main viaduct. The project director's 5.2 km figure was used in discussing the travel time on the elevated link. All three measurements describe the same Colombo port route from different angles, from the legal boundary to the construction detail and the driver's journey.
Where the elevated road runs
The route starts near the Kelanitissa power station area, one of the busy road junctions on the northern side of central Colombo. The gazette says the start point connects with the Kelanitissa System Interchange, close to the Colombo-Katunayake Expressway and Colombo-Kandy Road. Those connections matter because they let traffic approach the port corridor from the airport highway or from the Kandy road corridor before entering the elevated route.
The road then runs over Colombo Port land and internal port roads and finishes near Chaithya Road, close to the Galle Face side of the city. That placement gives the corridor two jobs at once. It can carry vehicles toward the port's internal network, and it can carry traffic toward the central area near Galle Face once the unfinished section is complete.
Road planners call the large crossing over other roads a viaduct. Instead of turning vehicles onto local streets, the elevated deck lifts them above those streets. The average width of 23.5 meters gives room for the carriageways and the structures that carry traffic across the port area. The road's position above port land also explains why the ramps matter so much: they are the places where traffic can join or leave the elevated path.
Three interchanges, with one still unfinished
The gazette schedule lists three interchanges on the expressway. Two are at Ingurukade and the Port of Colombo. Both provide exclusive links directly into the port's internal road network, which means vehicles using those ramps can reach port roads without joining the surrounding city streets first.
The third interchange is at the Port City and Galle Face end. It is not complete. The schedule attached to the minister's order, the part of the gazette that lists the physical features of the road, describes the site in exact terms.
Provision for Future Ramp Connection with partially completed Ramps.
The entrance and exit ramps at Ingurukade and the Port of Colombo are structures with a single lane, made with steel and concrete girders. Girders are the strong beams that carry the weight of a bridge deck. At the Port City and Galle Face interchange, the partially completed entry and exit ramps are viaducts with two lanes.
The difference in ramp design shows where the project stands. The port links are built, while the city end has been kept ready for later work. Until those future ramps are connected, the Galle Face end remains a future connection rather than a working route.
How much time could drivers save?
Supun Abeywickrama said the 5.2 km elevated route could be travelled in about five to six minutes. He said drivers using Baseline Road during peak traffic hours take 40 minutes or more to enter Colombo. If the estimate is reached, the trip would be about 34 to 35 minutes shorter at peak, or roughly 85 percent less travel time.
The comparison explains why the road has drawn attention. Baseline Road carries a mix of local traffic, buses, commercial vehicles and cars trying to enter the city. Junctions and traffic lights slow that flow. An elevated road with ramps can keep through traffic above those delays and give drivers a more direct path.
Abeywickrama said the second phase will give motorists direct access to Colombo Port. He also said plans are under way to extend the road to Galle Face. Once the road is complete and opened to the public, motorists travelling from Katunayake Airport through the expressway network are expected to reach central Colombo without dropping down into the slowest surface streets.
Timeline of the declaration and works
The road's status and construction moved through several dated steps in November 2026. The key moments are listed below, including the dates the government gave for night ramp closures.
- November 13, 2026: Gazette Extraordinary No. 2514/36 declared the stretch a national highway.
- November 23, 2026: Gazette Extraordinary No. 2516/02 declared the 5.729 km road an expressway under Section 9(1)(a) of the National Thoroughfares Act.
- November 23 to December 1, 2026: The Road Development Authority imposed nightly ramp closures at Ingurukade for connection works between the New Kelani Bridge and the elevated highway.
- Expected soon: Construction of the section from Colombo Port to Galle Face was expected to begin.
- After completion: The road was expected to open for public use.
The timeline shows why November 23 was a busy date. The same day that the expressway gazette was published, road crews began a narrow window of night works at Ingurukade to connect the new elevated link with the existing highway.
Night closures at Ingurukade
The Road Development Authority imposed nightly closures at the Ingurukade Interchange from November 23 to December 1. The closures were for connection works linking the New Kelani Bridge with the Port Access Elevated Highway. Drivers were advised to use alternative routes through Peliyagoda and Orugodawatta during the night works.
Night work is often used for bridge connections because crews can close a ramp for a few hours with less traffic than during the day. For drivers, the practical effect is a change of route at night rather than a permanent change. The advice to use Peliyagoda and Orugodawatta gave motorists known roads to avoid the closed ramp.
Ingurukade is one of the two interchanges with direct access to the port's internal road network. Work there is therefore not just a small ramp repair. It is the point where the elevated highway can be tied into the wider route toward the New Kelani Bridge and the airport expressway corridor.
What changes for Colombo drivers
The biggest change for drivers is the possibility of a continuous route where vehicles can move faster from the northern expressway approach toward the port and central Colombo. The declaration gives the road expressway status. The construction link, once complete, is meant to remove the need to descend into crowded streets before reaching the port area.
For a commuter coming from Katunayake Airport, the intended route becomes simpler. The driver can stay on the expressway network, use the new link near the Kelanitissa and New Kelani Bridge area, then take the elevated road toward the port or continue toward Galle Face when those ramps are ready.
For port traffic, the two exclusive interchanges at Ingurukade and the Port of Colombo offer direct roads into the port's internal network. That can keep port vehicles on a route designed for them, instead of mixing with local traffic at street junctions. The road's elevated design also crosses internal port roads without stopping traffic on the deck above.
What the port gains from direct access
Colombo Port sits close to dense city streets, where freight movement and commuter traffic compete for space. The elevated expressway creates a separate path into the port area. Its two port interchanges are the key feature in the gazette schedule because they connect directly to the internal road network.
The main viaduct was built over Colombo Port land and internal port roads. That detail explains how the design works in practice. The elevated deck passes above roads inside the port while the ramps at Ingurukade and the Port of Colombo provide the points where vehicles can enter or leave that network.
The unfinished Port City and Galle Face end is the part that would extend the benefit beyond port access. If the future ramps are completed, the same corridor could feed traffic toward the city side near Galle Face, closing the gap between a port road and a central Colombo route.
What is still not finished
The expressway declaration does not complete every ramp. The Port City and Galle Face interchange remains partially built, and the gazette schedule reserves space for a future ramp connection. The project director did not give an exact date for construction from Colombo Port to Galle Face, and no public opening date was given for the elevated link or the full route.
The November 23 to December 1 closures have fixed dates, but the later works depend on construction progress and ramp completion. Drivers should expect the road to become more useful step by step rather than all at once.
The next dated milestone is the end of the night closure period on December 1, 2026. After that, the visible question for Colombo will be when the Port City ramps move from partially completed structures to working entry and exit points.
Why the legal classification matters
Road labels can sound technical, but they shape how a route is planned and managed. A national highway is a major road in the national network. An expressway is a road intended for faster movement, with access controlled through interchanges and ramps instead of ordinary junctions.
The National Thoroughfares Act, No. 40 of 2008, is the law under which the minister issued the order. Section 9(1)(a) is the specific power used for the declaration. Naming the section shows the legal route taken by the government and gives readers a way to find the power used for the declaration.
For the Colombo corridor, the legal status matches the physical design. The road is elevated, has an average width of 23.5 meters, runs over port land and internal roads, and uses interchanges at Ingurukade and the port. The unfinished ramps at Galle Face are the remaining piece before the route can serve the full path described in the project plans.
Key Points
The story comes down to a legal change, a construction push and one unfinished city connection.
- Gazette Extraordinary No. 2516/02, published on November 23, 2026, declared the 5.729 km Port Access Elevated Expressway an expressway.
- Transport Minister Bimal Niroshan Rathnayaka signed the order under Section 9(1)(a) of the National Thoroughfares Act, No. 40 of 2008.
- The road runs from Kelanitissa Power Plant Junction to near Chaithya Road and has an average width of 23.5 meters.
- The main structure is a 5,132 meter viaduct over Colombo Port land and internal port roads.
- Ingurukade and Port of Colombo interchanges provide direct links into the port, while the Port City and Galle Face interchange remains partially complete.
- Project Director Supun Abeywickrama said the elevated route could take five to six minutes, compared with 40 minutes or more on Baseline Road at peak hours.
- Road Development Authority night closures at Ingurukade run from November 23 to December 1, with detours through Peliyagoda and Orugodawatta.