Malaysia Targets Up to Six Carbon Capture Hubs and RM170 Billion in Investment by 2050

12 Min Read
Malaysia Targets Up to Six Carbon Capture Hubs and RM170 Billion in Investment by 2050

A storage industry beneath the seabed

Malaysia plans to build three to six carbon capture, utilisation and storage hubs, attract RM160 billion to RM170 billion of investment and begin injecting carbon dioxide underground as early as 2030. Economy Minister Akmal Nasrullah Mohd Nasir launched the Malaysia CCUS Roadmap 2050: Towards Green Economy on 24 November 2026 at the APAC CCUS and Hydrogen Decarbonisation Summit 2026 at Pullman Kuala Lumpur City Centre. At peak operations, the industry could support 150,000 to 250,000 direct and indirect jobs.

Contents
  1. A storage industry beneath the seabed
  2. How the 27 initiatives fit together
  3. Four projects, four different tests
  4. The dates that will shape delivery
  5. What the CCUS Act requires
  6. Why Malaysia wants carbon from abroad
  7. The economic case for the East Coast
  8. CCUS within the wider energy transition
  9. Safety, environmental duties and public concern
  10. What happens next
  11. Key Points

Carbon capture, utilisation and storage, known as CCUS, has four basic stages. CO2 is separated from industrial exhaust or removed from the atmosphere, transported by pipeline, ship or another means, and then either used or placed in permanent geological storage. Storage without subsequent use is generally called CCS. Utilisation can turn the gas into fuels, building materials or agricultural products, although the quantity and duration of carbon storage differ between products.

The first hubs are planned for the east coast of Peninsular Malaysia. The area combines industrial clusters, oil and gas equipment and experience, and numerous depleted offshore reservoirs. A depleted reservoir is a geological formation from which oil or gas has already been produced, leaving space that may be suitable for CO2. The roadmap schedules the first hub, with storage capacity of 10 million tonnes of CO2 a year, to be operating by 2030. Shared pipelines and storage sites are intended to spread costs among factories rather than requiring every emitter to build its own system.

Advertisement

How the 27 initiatives fit together

The roadmap contains four strategic pillars, four supporting enablers and 27 initiatives. Fourteen initiatives concern physical development of the industry. The other 13 cover regulation, finance and incentives, worker training and public education.

  • Develop CCUS hubs through clusters, beginning on the east coast of Peninsular Malaysia.
  • Provide carbon capture and storage services for emissions produced elsewhere in the region.
  • Build Malaysian technology and industrial capabilities.
  • Use the industry to support economic development on the East Coast.

Steel, cement, refining and chemical production are central to the plan because some of their emissions come from industrial processes and high temperatures that cannot easily be removed by switching electricity supplies. Capturing those emissions could give existing plants a way to reduce their output of greenhouse gases while other technologies develop.

The commercial measures include tax allowances and incentives, carbon credit issuance, carbon accounting, licensing and agreements between countries. Carbon accounting would track how much CO2 is captured, transported, used or stored. The government expects these mechanisms to reduce the amount of capital each project must bear, improve project finances and make it easier to raise money. Storage contracts and sales of products made with captured CO2 would provide other possible sources of revenue.

Advertisement

Four projects, four different tests

The flagship projects examine different parts of the CCUS chain, from capturing industrial exhaust to transporting and storing CO2 offshore.

The Southern CCS Hub, also described as the East Coast, Peninsular Malaysia Offshore CCS Project, is led by PETRONAS with Mitsui and TotalEnergies. It would include a terminal in Kuantan, Pahang, capable of receiving liquefied CO2, and a pipeline running 245 kilometres offshore to the depleted Duyong field. The facility is designed to store up to five million tonnes of CO2 a year beneath the seabed. Akmal said capture activity would take place in Terengganu while the terminal would be in Pahang, giving both states a role.

The National Carbon Capture Project is led by the Ministry of Investment, Trade and Industry, with Sirim Bhd conducting the pilot. It will test capture equipment on exhaust from steelmaking at Eastern Steel Sdn Bhd in Kemaman, Terengganu. Engineering, procurement, construction and commissioning, collectively called EPCC, are targeted for 2027 to 2030. This stage would move the work from design and equipment purchases into construction and testing.

Tenaga Nasional Bhd is responsible for the other two projects, both using exhaust from its Jimah East coal power plant. Project Dragon is testing capture of CO2 and its conversion into products such as synthetic fuels. Project Chlorobloom uses the gas to cultivate microalgae that could supply aquaculture, animal feed and fertiliser. The ministry also identifies possible uses in concrete cured with CO2, aggregates and insulation, greenhouse cultivation, water treatment, industrial pH control, geothermal systems and energy storage.

Advertisement

The dates that will shape delivery

The programme combines legislation, pilot plants, commercial studies and offshore construction over several years.

  • 25 March 2025: Malaysia passed the Carbon Capture, Utilization and Storage Bill 2025.
  • 24 November 2026: The economy minister launched the national roadmap.
  • 2027 to 2030: EPCC work is targeted for the National Carbon Capture Project.
  • Fourth quarter of 2027: An assessment of an East Coast industrial CCUS cluster is due for completion.
  • 2030: The government aims for Malaysia's first CO2 injection as early as this year, while the first 10 million tonne hub is scheduled to be operational.
  • Fourth quarter of 2031: The roadmap's detailed project timetable lists first injections for PETRONAS's five million tonne offshore project.
  • 2050: The investment, employment, economic value and hub targets reach their final horizon.

Akmal said the PETRONAS project was expected to deliver the first commercial injection under the roadmap and identified 2030 as the target. The separate timetable giving the fourth quarter of 2031 for that project's first injections leaves the two schedules to be aligned. No explanation for the different dates was given at the launch.

Advertisement

What the CCUS Act requires

The CCUS Act 2025 supplies the legal foundation for licensing, CO2 movements between countries, monitoring and responsibility for storage sites. A legal summary by CMS explains that it applies to Peninsular Malaysia and the Federal Territory of Labuan. It does not apply to Sabah or Sarawak. Carbon storage projects in Sarawak are governed separately by the Land (Carbon Storage) Rules 2022.

The act establishes the Malaysia Carbon Capture, Utilization and Storage Agency to advise the government, supervise CCUS activities, manage storage resources and administer the Post-Closure Stewardship Fund. Its members include the secretary general of the ministry responsible for CCUS, the director general of the Department of Environment and up to six additional members appointed for their relevant experience and expertise.

Owners and operators of capture installations, CO2 transporters and users of captured CO2 must register with the agency. Permits are required to import captured CO2, assess potential geological storage formations and operate onshore or offshore storage sites. Operators must also ensure that each CO2 stream meets acceptance criteria designed to protect the integrity and safety of the storage operation.

An injection levy will finance government monitoring and corrective work. The money goes into the Post-Closure Stewardship Fund alongside government contributions and investment income earned by the fund. A site can close only after prescribed conditions are met and the agency issues a closure certificate. Operators remain responsible for monitoring, reporting, corrective action and remediation until those duties are formally transferred to the government. The legal summary published at the time of passage said Royal Assent was expected before 31 March 2025 and that accompanying regulations would provide further implementation guidance.

Advertisement

Why Malaysia wants carbon from abroad

Malaysia wants to sell permanent storage as a service to emitters in ASEAN and the wider Asia Pacific. Akmal introduced the ambition by referring to Norway's Northern Lights project, which demonstrates how CO2 can be captured in one country, transported across national boundaries and stored in monitored formations beneath the seabed.

Malaysia aspires to be the Northern Lights of the East.

Malaysia is discussing CCUS cooperation with Japan, South Korea and Singapore, with a memorandum of understanding expected in 2027. Akmal said cooperation between governments, common standards, transparent monitoring and clear responsibilities would be needed before other countries entrusted their CO2 to Malaysian storage sites. Bilateral agreements would also need to establish procedures for shipments and how emissions reductions are accounted for between the participating countries.

The ministry's CCUS overview, citing the Global CCS Institute, estimates Malaysia's storage capacity at 13.3 gigatonnes, equivalent to 13.3 billion tonnes. At the roadmap launch, Akmal gave a much larger figure of more than 150 billion tonnes of potential storage resources in depleted oil and gas fields and saline aquifers. A saline aquifer is porous underground rock containing water that is too salty for ordinary use. The launch did not reconcile the two resource estimates. The ministry presents the country's storage geology as a valuable resource that could serve both domestic and regional emissions, rather than as a dumping ground.

Advertisement

The economic case for the East Coast

The RM160 billion to RM170 billion capital target is equivalent to about US$38.8 billion to US$41.3 billion. It is separate from the projected US$200 billion to US$250 billion in cumulative gross value added. Gross value added measures the value created after subtracting the cost of inputs; it is not the amount investors spend building the projects.

The ministry's official key statistics attributes the gross value added range and an estimate of 200,000 direct and indirect jobs by 2050 to PETRONAS. The roadmap launch gave the wider employment range of 150,000 to 250,000 jobs at peak operations. Projections accompanying the legislation had previously described more than US$200 billion of investment over three decades and 200,000 potential jobs.

Akmal said Terengganu and Pahang could gain employment and industrial activity outside the Klang Valley. He also called for Malaysian companies to become suppliers and innovators, with technology transfer, local technical solutions and worker skills included in investment proposals. Oil and gas service companies, engineers and technicians could apply their experience with offshore facilities, pipelines and geological reservoirs to the new storage chain.

Possible businesses extend beyond storage fees. They include manufacturing with lower emissions, blue hydrogen and ammonia. Blue hydrogen generally means hydrogen made from natural gas while capturing much of the resulting CO2. Ammonia can be used in industry and can also serve as a way of transporting hydrogen, although each opportunity still requires viable costs and buyers.

CCUS within the wider energy transition

CCUS is one of six levers in Malaysia's National Energy Transition Roadmap, which contains 69 action items. The other levers and their stated targets are:

  • Energy efficiency: savings of 23% in industry and commerce.
  • Renewable energy: 70% of installed electricity capacity.
  • Hydrogen: production of up to 2.5 million tonnes of green hydrogen a year.
  • Bioenergy: capacity to produce 3.5 billion litres of biofuel.
  • Green mobility: public transport accounting for 60% of urban travel.

Together, the initiatives are projected to reduce greenhouse gas emissions in Malaysia's energy sector by 32% from the 2019 baseline by 2050, taking per capita emissions to 4.3 metric tonnes of CO2 equivalent. CCUS addresses emissions that remain at industrial facilities, while the other measures reduce energy demand, change electricity supply and alter transport. Akmal said renewable energy would still need to expand alongside efforts to manage continuing industrial emissions.

Advertisement

Safety, environmental duties and public concern

The economy ministry says the Intergovernmental Panel on Climate Change recognises CCUS as a safe and effective strategy for reaching net zero emissions around the middle of the century. Its overview stresses that safe storage depends on suitable geology, robust monitoring, stringent regulation and proper management to prevent CO2 from leaking back into the atmosphere.

Environmental groups have raised concerns about project costs, leakage risks and responsibility for sites after they close. The legal analysis of the act identifies two additional criticisms: storing imported CO2 does not itself reduce Malaysia's domestic emissions, and the legislation does not expressly require an environmental impact assessment for every proposed CCUS project. Those issues matter because the country could earn storage revenue while still needing separate measures to cut emissions produced within its own borders.

Akmal said the government needed to engage civil society organisations, handle the programme transparently and consider effects on local communities. The act's monitoring duties, injection levy and stewardship fund establish a financial and administrative structure for sites after closure. Their practical effectiveness will depend on detailed regulations, site assessments, enforcement and the quality of monitoring over the decades during which CO2 remains underground.

What happens next

The Ministry of Economy has commissioned three studies: an action plan for implementing the roadmap, an assessment of emissions clusters and CCUS business models, and work on an East Coast industrial CCUS cluster. The cluster assessment is scheduled for the fourth quarter of 2027. Project sponsors and the government must also assess proposals, secure approvals and funding, design facilities and plan safety measures before injections begin.

Regional agreements, tax measures, carbon credit arrangements and further operating rules must develop alongside the engineering work. No timetable was announced for every later hub, and the launch did not allocate the RM160 billion to RM170 billion investment target among individual projects. The nearest dated milestones are the 2027 cluster assessment, regional cooperation talks and the capture project's EPCC programme.

Key Points

  • Malaysia targets three to six CCUS hubs and RM160 billion to RM170 billion of investment by 2050.
  • Projected cumulative gross value added is US$200 billion to US$250 billion, with 150,000 to 250,000 jobs at peak operations.
  • The first hubs will be on Peninsular Malaysia's east coast, with a national ambition for initial CO2 injection as early as 2030.
  • The PETRONAS, Mitsui and TotalEnergies hub would use a Kuantan terminal, a 245 kilometre offshore pipeline and the Duyong field to store five million tonnes a year.
  • Other flagships will test carbon capture at a Terengganu steel plant and conversion of power station CO2 into fuels and algae products.
  • The CCUS Act 2025 establishes registration, permits, an injection levy and duties for monitoring and remediation after storage sites close.
  • Malaysia is discussing regional storage cooperation with Japan, South Korea and Singapore, while environmental concerns include leakage, costs, imported emissions and assessment requirements.
Share This Article