A new tunnel brings Haneda closer to central Tokyo
East Japan Railway Co. began tunneling on November 16, 2026, for a rail connection designed to take passengers from Tokyo Station to Haneda Airport in about 18 minutes without changing trains. The Haneda Airport Access Line, a tentative name, is scheduled to open in fiscal 2031, the year ending March 2032.
Contents
- A new tunnel brings Haneda closer to central Tokyo
- What the tunneling machine will do
- Two construction teams will meet beneath a canal
- How the Tokyo Station route will work
- Where passengers will arrive at Haneda
- Waterfront and Shinjuku routes offer different gains
- How the project reached this stage
- Why the cost and city connection matter
- A Haneda–Narita train is also under consideration
- Key Points
The project combines about 5 kilometers of new railway with 7.4 kilometers of improvements to existing infrastructure, including a former freight line. Its estimated cost is 280 billion yen, including about 70 billion yen for related tunnel structures and other work under the national government's airport development program.
For passengers, the main change will be a simpler trip. Traveling from Tokyo Station to Haneda currently takes about 30 minutes and requires a transfer, commonly at Hamamatsucho or Shinagawa. An 18 minute journey would save about 12 minutes, cutting that travel time by roughly 40 percent.
The new airport station will sit underground between Terminals 1 and 2. Beyond central Tokyo, planned services could let passengers from the Utsunomiya, Takasaki and Joban lines stay on the same train all the way to the airport.
JR East is developing three routes around the new airport connection: East Yamanote, serving Tokyo Station; a waterfront route toward Shin-Kiba; and West Yamanote, serving the Shibuya and Shinjuku side of the capital. Their progress differs. East Yamanote is being developed first, while JR East is working toward opening the waterfront connection alongside it. West Yamanote has no opening date.
What the tunneling machine will do
The machine starting from near Tokyo Freight Terminal in Shinagawa Ward is called Haruton, a name formed from the initials of Haneda Airport Access Line Tunnel. It measures about 11.8 meters across and 12.7 meters from front to back. Assembly began in April and finished in October, before the construction site was shown to journalists on November 6.
Haruton uses a rotating cutting face to remove soil. Behind that face, workers and machinery assemble curved sections that form the tunnel wall. The machine then pushes against the completed sections to move forward.
JR East has chosen a slurry shield system. In simple terms, a liquid mixture supports the ground at the cutting face, while excavated soil is mixed with that liquid and pumped back to the surface. The project also uses a method called Loss Zero, allowing the machine to advance while tunnel wall sections are being assembled, shortening pauses in the work.
The planned excavation rate is about 10 meters a day, with roughly a year allowed to reach the underground joining point. The finished tunnel will have an internal diameter of about 10.6 meters, enough for tracks in both directions, with an evacuation passage below them. After excavation, the machine is to be dismantled underground and removed.
Two construction teams will meet beneath a canal
JR East is excavating about 2.3 kilometers from the Tokyo Freight Terminal side. The national government is responsible for construction within the airport development area, digging from the airport side toward the railway company's tunnel.
The government section is described as about 1.9 kilometers in the initial project account, while more detailed construction descriptions give lengths of 2.4 kilometers and 2.7 kilometers. The new railway section as a whole is consistently described as roughly 5 kilometers long.
The two tunneling operations are planned to meet beneath the Keihin Canal, about 40 meters below ground. At its deepest point, the tunnel will be about 45 meters underground. Joining the sections will create the continuous passage between the existing railway infrastructure and the airport.
Work elsewhere includes track changes around Tamachi Station, repairs to existing bridges and track installation within Tokyo Freight Terminal. These jobs help explain why the project extends well beyond the new tunnel: the airport connection must also fit into a working railway network.
How the Tokyo Station route will work
The East Yamanote route will reuse and improve a former freight railway between Tokyo Freight Terminal and the area near Tamachi. It will connect with the Tokaido Line, allowing airport trains to reach Tokyo Station rather than ending at a separate terminal where passengers would have to change.
Through services are also planned onto the Ueno–Tokyo Line and the Utsunomiya, Takasaki and Joban lines. A through service means that a train continues from one railway line onto another while passengers remain in their seats.
That operating pattern could spread the benefit beyond people starting in central Tokyo. Travelers from northern parts of the metropolitan area could avoid a transfer with luggage, while Tokyo Station would provide connections with its wider network of local and intercity trains.
An operating plan has listed eight trains an hour and 144 trains a day on the East Yamanote route. If eight departures were spaced evenly, that would mean a train approximately every seven and a half minutes. Final fares, the detailed timetable and the exact opening day have not been announced.
Where passengers will arrive at Haneda
The new airport station is planned beneath a road between Terminals 1 and 2. Its island platform, a single platform with a track on either side, will be about 310 meters long and up to about 12 meters wide.
The station is planned on the first basement level. Its concourse will connect with Terminal 2 without a change in level, making the route easier for passengers pulling suitcases or using wheelchairs and strollers.
Terminal 3 is farther from the new station. JR East and Tokyo Monorail plan to coordinate connections to improve access to that terminal. Passengers will therefore need to consider which terminal their flight uses when choosing their route to the airport.
The 18 minute journey is the projected train travel time between Tokyo Station and the new airport station. Walking from a platform to an airline counter or departure gate will remain part of the passenger's trip.
Waterfront and Shinjuku routes offer different gains
The waterfront route would connect the airport railway with the Rinkai Line, giving access toward Odaiba and Shin-Kiba. Plans also envisage through services with the Keiyo Line toward destinations in Chiba Prefecture, including Maihama.
The projected Haneda–Shin-Kiba journey is 20 minutes, compared with 41 minutes now. That would save 21 minutes, slightly more than half the current travel time. JR East is coordinating with the parties involved to pursue an opening alongside East Yamanote in fiscal 2031.
The West Yamanote route would connect toward Osaki, Shibuya and Shinjuku through the Rinkai and Saikyo railway network. Its projected Haneda–Shinjuku journey is 23 minutes, down from 43 minutes, a saving of 20 minutes.
West Yamanote requires a new tunnel between the area around Oimachi Station and Tokyo Freight Terminal. With no opening schedule established, passengers on Tokyo's western side face a longer wait than those who would use the Tokyo Station route.
How the project reached this stage
JR East set out its ambition to improve Haneda access in its 2013 management vision and presented a basic construction plan in 2014. An early goal of opening part of the railway for the Tokyo Olympics gave way to the time required for environmental assessment and project preparation.
The project has since moved through approval, major construction and changes to protect historic infrastructure. Its key milestones include:
- 2019: JR East began the environmental assessment process for the proposed routes.
- 2021: The company announced national government approval for the East Yamanote route.
- June 2, 2023: A groundbreaking ceremony marked the official start of construction.
- April 2024: The planned starting point was moved about 100 meters south to preserve part of the historic Takanawa Embankment where it stood.
- November 6, 2026: JR East showed the tunnel construction site and machine to journalists.
- November 16, 2026: Tunneling began from the Tokyo Freight Terminal side.
- Fiscal 2031: The airport connection and East Yamanote route are scheduled to open, with a simultaneous waterfront opening being pursued.
The Takanawa Embankment dates to the Meiji era and formed part of Japan's early railway infrastructure. Moving the connection point toward Shinagawa allowed part of that structure to remain in place while the new airport railway proceeded.
Why the cost and city connection matter
JR East's estimated investment has fallen from an initial 300 billion yen to 280 billion yen following savings during investigation and design. That is a reduction of 20 billion yen, or about 6.7 percent. Reusing freight railway infrastructure is a central feature of the construction plan.
The airport connection is also approaching completion at a time when several redevelopment projects around Tokyo Station are scheduled to finish around 2030. A direct railway would give businesses, visitors and residents a simpler connection between that district and Haneda.
Satoshi Yamasaki, head of JR East's Haneda Access Project Center, described the wider purpose of the connection:
The connection to the Tokyo metropolitan area's railway network is extremely significant, and JR East also wants to contribute to strengthening the airport's international competitiveness and functions.
JR East's comparison materials list airport rail journeys of 20 minutes for Beijing Capital International Airport, 16 minutes for Atlanta and 15 minutes for London's Heathrow. The planned 18 minute Tokyo Station service would fall within that range, compared with Haneda's current journey of about 30 minutes.
For travelers, the practical value is both the shorter journey and the removal of a transfer. For the railway, success also depends on connecting airport trains reliably with existing services across a large part of the metropolitan area.
A Haneda–Narita train is also under consideration
JR East President Yoichi Kise expressed strong interest at a November 10 press conference in running direct trains between Haneda and Narita airports in time for the Haneda Access Line opening in fiscal 2031.
Kise cited a government estimate that the number of Narita Airport users arriving by rail would reach about 1.6 times the fiscal 2023 level by fiscal 2035. That would represent growth of roughly 60 percent and would increase the importance of railway capacity serving Narita.
A direct connection could help international visitors arriving at Narita who then need to catch a domestic flight from Haneda. Kise's comments set out an ambition; a route, journey time and operating plan for that service have yet to be announced.
The immediate construction priority remains the link beneath the canal and into Haneda. Completing it would give JR East the airport connection needed for the planned Tokyo Station service and for further through services across its network.
Key Points
- JR East began tunneling on November 16, 2026, for a Haneda Airport railway scheduled to open in fiscal 2031.
- The planned Tokyo Station journey is about 18 minutes without a transfer, compared with about 30 minutes today.
- The project combines roughly 5 kilometers of new railway with 7.4 kilometers of existing infrastructure improvements.
- The estimated cost is 280 billion yen, including related national airport development work.
- A new underground station will serve Terminals 1 and 2, with connections planned for Terminal 3.
- JR East is pursuing a waterfront opening alongside East Yamanote; the Shinjuku route has no opening date.
- A direct Haneda–Narita service is an ambition, with operating details still undecided.