Trump leaves Manila without a Pax Silica signing
President Donald Trump's visit to Manila on November 17 and 18, 2026, ended without an agreement for the proposed Pax Silica industrial hub in New Clark City, Capas, Tarlac. The site covers roughly 1,620 hectares, or about 4,000 acres. Its promoters envision semiconductor manufacturing, mineral processing and other advanced industries. Its opponents see a more immediate question: whether Aeta families and farmers will lose land, water and livelihoods before any promised factory opens.
Contents
- Trump leaves Manila without a Pax Silica signing
- What the Philippines has offered
- Why Aeta families fear relocation
- Can Tarlac supply the water and power?
- The investment promise is still a projection
- What House Bill 11758 would change
- Protests bring arrests and a rights investigation
- Who would capture the economic gains?
- What happens next
- Key Points
Senate President Sherwin Gatchalian said US Secretary of State Marco Rubio addressed the dispute during a state luncheon at Malacañang Palace on November 18. Gatchalian recounted Rubio's message in a radio interview.
He said he knows there are many issues and problems. We should not rush things and should give the Philippine government time to address these issues.
Gatchalian said the concerns include both Pax Silica and the Luzon Economic Corridor. US Ambassador Lee Lipton and President Ferdinand Marcos Jr. had already ruled out a signing during the visit. When Trump referred a question about the initiative to Lipton, the ambassador gave an unambiguous answer.
There will be no signing. There is no signing.
Marcos added, "No, not on this trip. We are not covering that on this trip." Philippine officials had previously hoped to conclude the framework agreement before the end of 2026. The Bases Conversion and Development Authority (BCDA), which is developing the site, had also targeted a November signing.
The diplomatic pause followed days of street opposition. Demonstrators in Manila on November 16 carried "Trump Out" signs and called for Pax Silica to be rejected. Marcos, who supports the project, was also a target of the rallies.
What the Philippines has offered
Pax Silica is an initiative led by the US State Department to make supplies of semiconductors, artificial intelligence hardware, critical minerals and related technologies less dependent on China. A supply chain is the network of mines, processors, component makers, factories and transport links needed to produce a finished technology. Disruption at one point can delay everything that follows.
The United States launched the initiative in December 2025 with Australia, Japan, South Korea, Singapore, the United Kingdom and Israel as the other founding signatories. It has since expanded to more than two dozen countries and regional partners. At a second Pax Silica Summit in Washington in June 2026, the United States and close to three dozen economies also signed a Joint Statement on AI Opportunity.
- December 2025: Pax Silica launches with seven founding signatories.
- April 2026: The Philippines joins and offers land in New Clark City for the initiative's first planned physical hub.
- July 2026: Marcos promotes the project in his State of the Nation Address, promising quality jobs and stronger industrial competitiveness.
- October 2026: Six members of the House of Representatives file legislation to govern an Advanced Industries Zone.
- November 14 to 18: Regional meetings and Trump's visit bring protests, arrests and clarification that no hub agreement will be signed.
- December 2026: Aeta residents say they were verbally told to expect relocation, while Philippine officials retain a target of completing negotiations by the end of the year.
Participation in the declaration does not itself settle the Tarlac development. The hub still requires a framework and master agreement. Those documents will determine the commercial and legal arrangements, including any commitments on investment, technology transfer, training and local employment.
Why Aeta families fear relocation
Human Rights Watch said on November 16 that the project could displace Indigenous residents and farmers in Capas. Its findings center on the Aeta Hungey community in Sapang Kawayan, whose members have sought recognition of their ancestral domain since the 1990s. Without a title, residents say their homes, farms, water sources, burial grounds and places of worship remain exposed to decisions made elsewhere.
Community chieftain Petronila Capiz-Muñoz said BCDA officials verbally told residents that they could be moved as early as December into housing units measuring 30 square metres. She described the proposed accommodation as a "matchbox." The relocation site would be three kilometres away and would not provide access to the streams residents now use. Farming families also fear that a housing unit cannot replace the fields that supply their food and income.
The dispute was already visible when Aeta communities raised land fears in October. A survey by Syracuse University professor Arnisson Andre Ortega found that planned construction would encroach on land used by at least three Aeta villages. Gloria Capiz-Estabillo, an Aeta Hungey elder aged 76, said residents had already been told to leave. Then BCDA chief Joshua Bingcang denied that anyone would be displaced and pointed to the absence of a formal ancestral domain title.
Maninging Vilog, a teacher and advocate for Aeta communities, connected the Tarlac dispute to a broader objection to foreign control during the November protests.
They have been grabbing our lands. They have been grabbing our economy. … Pax Silica is just for the U.S. It's not for us.
The Makabayan bloc has put the possible displacement at 2,000 Aetas. Separate reports that BCDA offered P30 per square metre for ancestral land intensified the anger. Palace press officer Claire Castro subsequently sought clarification about documents on which some Aeta community members had reportedly placed thumbmarks, allegedly surrendering rights for the project. BCDA has also committed to no Pax Silica evictions until funds and rights are secured. How that commitment will be enforced, and who will qualify for protection or compensation, has not been set out publicly.
Can Tarlac supply the water and power?
BCDA estimates that the fully developed site would require 65 million to 90 million liters of water every day. Bingcang's earlier estimate of 16 million to 24 million gallons daily converts to roughly 61 million to 91 million liters, broadly matching the newer range. A higher estimate used in public debate puts consumption at 130 million liters a day and the annual requirement at 39 billion liters after rainfall and reservoir capacity are considered. No final water plan reconciling the projections has been published.
The concern extends beyond the industrial estate. Capas residents depend on streams and farmland, while a projected strong El Niño through 2027 could intensify drought conditions. Semiconductor plants can recycle water, and rates of at least 40% are achievable, but the equipment adds to investment costs. Systems combining membrane biological treatment with reverse osmosis, a process that forces water through a very fine filter, have been estimated at $3 million to $10 million for each fabrication plant.
Electricity presents a second constraint. Steve Chien, a vice president of Taiwan Association, Inc., said New Clark City's projected demand is 2,000 megawatts, while only about 200 megawatts is available. That is roughly one tenth of the projected requirement. Bingcang previously gave an estimate of about 3 gigawatts, equivalent to 3,000 megawatts, showing the scale that earlier planning considered.
Philippine industrial power rates have been placed at $0.14 to $0.22 per kWh, approximately twice the rates in Vietnam and Indonesia. Prospective manufacturers must therefore consider not only whether enough electricity can be delivered, but also what it will cost. Utility arrangements remain unsettled, including who will finance new generation, transmission lines, reservoirs, pipes and recycling facilities.
The investment promise is still a projection
Government projections say the hub could attract $40 billion to $70 billion over 30 years. During the protests, administration statements cited 100,000 to 130,000 jobs. BCDA has also projected 130,000 to 190,000 direct jobs over several decades, while another BCDA presentation gives 190,000 direct jobs and 800,000 indirect and induced jobs. Indirect jobs are created among suppliers and service providers; induced jobs arise when workers spend their wages. None of these figures represents people already hired.
The initial phase covers 500 hectares and targets 10 to 20 firms and $10 billion in investment by 2028. BCDA vice president Erwin Kenneth Peralta told visiting Taiwanese businesspeople on November 21 that full development would take 20 to 25 years. The first five years would be devoted to land preparation, roads and utility lines before factories are built.
Finance Secretary Frederick Go said in July that Taiwanese electronics manufacturer Foxconn was poised to become the anchor locator, meaning the main tenant. Taiwan participates in Pax Silica without signing its declaration. It was also the largest source of approved foreign investment in the Philippines in the third quarter, with P76.27 billion, nearly half of the total, according to the Philippine Statistics Authority. Approved investment, however, is not the same as money already spent on construction.
Best Chang, president of the Subic Bay Taiwan Chamber of Commerce, said interested Taiwanese companies are waiting for Washington to sign agreements and demonstrate that it will carry out its commitments.
For Pax Silica to move from plans to actual investment in the Philippines, the United States needs to follow through with signed agreements for the proposed hub, concrete commitments, and implementation. Without that, even the most detailed supporting plans risk remaining plans on paper.
Chang said site visits and expressions of interest should not be treated as firm commitments. Companies will subsequently examine power, water, workers, transport, logistics and the predictability of regulations and incentives. Tomas Buenaventura, an Asia-Pacific analyst at the Armed Conflict Location and Event Data Project, said investors fear the Philippines could "drop the ball and lose the planned hub to other Pax Silica partners." He cited Indonesia's Rempang Eco-City as another development where disputes over land acquisition and relocation contributed to delays.
What House Bill 11758 would change
House Bill No. 11758, titled the Advanced Industries Development Act, was filed in October by six administration-allied lawmakers led by Deputy Speaker Ronnie Puno. The other authors are Miguel Luis Villafuerte, Albert Garcia, Alfredo Maranon III, Rolando Valeriano and Jolo Revilla. It would create an Advanced Industries Zone and an Advanced Industries Development Authority (AIDA).
AIDA would have authorized capital of P50 billion and a board of 11 governors, including a chairperson appointed by the president. It would administer the zone, oversee projects, fix and collect fees and enter contracts. The authority would also receive a renewable franchise lasting 25 years to construct, operate and maintain power and water distribution systems inside the zone.
A company seeking status as a qualified enterprise would need at least P15 billion in investment capital, excluding land value. Eligible activities include semiconductor design, fabrication, assembly, testing and packaging; robotics and advanced materials; computing infrastructure for artificial intelligence; processing of critical minerals; scientific research; and energy facilities. Qualified enterprises would receive an income tax holiday lasting seven years from the start of commercial operations, followed by a special corporate income tax or enhanced deductions. They would also receive exemptions from value added tax and customs duties.
The bill says ancestral lands cannot be declared alienable and disposable, a legal classification used for land that may be opened to private ownership. It also gives hiring preference to Capas residents, members of Indigenous communities whose ancestral domains lie within or beside the zone, and people displaced by the project.
The measure remains at an early stage. It has been referred to the economic affairs committee but has not been tackled, has no Senate counterpart and is not yet a Palace priority. Its treatment of data centers also requires clarification. The bill includes them among eligible computing infrastructure, while Marcos said in Shenzhen, China, "There will be no data centers" at the Clark hub. He said he was "a little bit perplexed" by the protests "because number one, there is no deal yet." Data centers are large facilities filled with computers that store and process information; their cooling and continuous operation can require substantial water and electricity.
Protests bring arrests and a rights investigation
ACLED recorded 36 demonstrations against Pax Silica from April 22 to November 16, including 21 in November. Participants included students, workers, farmers, Indigenous advocates and environmental groups. Their objections ranged from ancestral land and resource consumption to national sovereignty and the possibility that the project could serve US strategic interests without delivering enough local benefits.
Human Rights Watch documented at least 245 arrests during the summit protests, including at least 20 journalists. Broader police and media tallies put detentions at nearly 300 across Manila, Parañaque and Muntinlupa. Bagong Alyansang Makabayan leader Renato Reyes described the crackdown as the largest single day of police arrests since Marcos took office in 2022. Police officials said the arrests involved assemblies held without permits, property damage and injuries to officers during confrontations.
The Commission on Human Rights announced an investigation on November 18. Its statement cited reports involving the apprehension of minors, injuries, detention conditions and delays in gaining access to detainees. It called for due process and maximum tolerance, a policing principle that requires restraint when managing public assemblies.
Who would capture the economic gains?
The Philippine debate is unfolding alongside a broader regional push for digital investment. All 11 ASEAN member states signed the Digital Economy Framework Agreement on November 14, covering digital trade, data flows between countries, electronic payments, cybersecurity and emerging technologies. It is expected to take effect in early 2027. Australia, a founding Pax Silica member, announced a separate digital cooperation package at the ASEAN-Australia Summit on November 16, including support for artificial intelligence safety standards and workforce development.
The Philippines already has industrial experience on which to build. An OECD study in 2024 identified strengths in semiconductor assembly, testing and packaging, with a smaller presence in chip design. The proposed hub lies within the Luzon Economic Corridor, which connects Subic, Clark, Manila and Batangas. The Subic-Clark-Tarlac Expressway links Tarlac with the Clark area and Subic's seaport, giving manufacturers potential routes for equipment and exports.
IBON Foundation argues that the initiative could deepen dependence on foreign companies rather than create an industrial sector owned by Filipinos. Alvin Camba has taken a conditional position, writing in June 2026 that the country could enter more valuable manufacturing if it negotiates for technology transfer, local hiring and training. Without those terms, the Philippines could remain concentrated in less valuable stages of production.
Louie C. Montemar, a fellow of the Stratbase Institute and associate professor at the Polytechnic University of the Philippines, supports pursuing the initiative under what he calls productive sovereignty. He wants Filipino engineers and suppliers to gain the ability to redesign components, improve production lines and win subsequent contracts. He has proposed using the Tatak Pinoy Act to finance equipment upgrades for local firms, alongside paid apprenticeships and shared research and testing facilities.
Montemar also calls for public milestones covering permanent jobs, wages, contracts for Philippine suppliers and research work performed in the country. Before approval, he says authorities should disclose land terms, expected power and water demand, infrastructure costs and who will pay them. That accounting would allow households to judge the project as potential employees, taxpayers and neighbors, rather than relying on the largest investment headline.
What happens next
No new signing date has been announced. BCDA has been awaiting Washington's response to its draft framework. Trade Undersecretary and Board of Investments Managing Head Ceferino Rodolfo said the master agreement still required full negotiations, while retaining hope that it could be signed before the end of 2026. Asked what remained unfinished, his answer was blunt: "The master agreement itself, the whole thing."
Several practical tests now run in parallel. Aeta residents are seeking protection before the December relocation they say was described to them. Legislators have yet to begin committee work on House Bill 11758. Investors are watching for signed US commitments and credible utility plans. Philippine Representative Antonio Tinio has cautioned that "it's far from certain" that construction will begin and the project will succeed. The government's initial industrial target is 2028, but its investment and employment figures will remain projections until land, rights, water, power and commercial terms are settled.
Key Points
- Trump's November 2026 Manila visit produced no Pax Silica hub agreement.
- Marco Rubio told Sherwin Gatchalian that Philippine concerns should be resolved before proceeding.
- The New Clark City site covers roughly 1,620 hectares, with investment projections of $40 billion to $70 billion.
- Aeta Hungey residents fear relocation from ancestral land and loss of farms, streams and burial grounds.
- BCDA estimates full water demand at 65 million to 90 million liters daily, while major power and utility gaps remain.
- House Bill 11758 proposes tax incentives and a new zone authority but remains stalled at an early legislative stage.
- At least 245 people were arrested during summit protests, and the Commission on Human Rights opened an investigation.
- Taiwanese investors want signed US commitments before turning interest in the hub into actual investment.