India's Infrastructure Bill Swells by ₹3.28 Lakh Crore as 1,862 Central Projects Outrun Their Budgets

9 Min Read
India's Infrastructure Bill Swells by ₹3.28 Lakh Crore as 1,862 Central Projects Outrun Their Budgets

A Bill That Grew by ₹3.28 Lakh Crore

India's central government is keeping watch on 1,862 infrastructure projects, each costing more than ₹150 crore, spread across 17 ministries and departments. In its monthly report for October 2026, released on Wednesday, the Ministry of Statistics and Programme Implementation put the combined original cost of those projects at ₹34,82,840 crore and their revised cost at ₹38,11,292 crore.

Contents
  1. A Bill That Grew by ₹3.28 Lakh Crore
  2. Nearly Half the Bill Has Already Been Paid
  3. Transport and Logistics Carry Most of the Pipeline
  4. Which Ministries Hold the Biggest Bills
  5. Where the Projects Sit on the Timeline
  6. What Finished in October and What Joined the List
  7. Finance Ministry Puts Cost Escalation Under the Scanner
  8. Key Points

A cost overrun is the distance between what a project was expected to cost when it was approved and what it is now forecast to cost. Here that distance is ₹3,28,452 crore, or ₹3.28 lakh crore. A lakh crore is one trillion rupees, which makes the gap about ₹3.28 trillion on a final bill of about ₹38.11 trillion.

The report gives the total bill and the total number of projects it monitors. It does not say how many of the 1,862 individually breached their original budgets, so the size of an average overrun cannot be worked out from it. The pipeline is split into 790 mega projects, each costing ₹1,000 crore or more, and 1,072 major projects below that line.

Nearly Half the Bill Has Already Been Paid

Money already spent on the 1,862 projects comes to ₹17.87 lakh crore, which is 46.88 per cent of their revised cost. Put plainly, close to 47 paise of every rupee on the revised bill has left the treasury, and the remaining 53 paise is still to be funded.

The ministry counts 649 projects, about 35 per cent of the total, as having crossed 80 per cent physical progress, meaning the work on the ground is more than four-fifths done. Another 326 projects, or 18 per cent, have crossed 80 per cent financial completion, meaning four-fifths of their budgeted money has been released.

Advertisement

Transport and Logistics Carry Most of the Pipeline

The transport and logistics sector holds 1,324 projects with a combined cost of ₹20.37 lakh crore, which is 71.1 per cent of the monitored projects and about 53.45 per cent of their aggregate cost. Energy follows with 229 projects worth ₹11.31 lakh crore, close to 29.68 per cent of the revised cost. Between them the two sectors account for 1,553 projects, or 83.4 per cent of the total, and roughly 83.11 per cent of the money.

Inside transport, roads and highways account for 972 projects. Inside energy, oil and gas has the largest number of projects at 104, while electricity generation carries the biggest bill at ₹4.27 lakh crore across 38 projects. Spending in the energy category has reached ₹4.47 lakh crore, or 39.49 per cent of its cost.

Advertisement

Which Ministries Hold the Biggest Bills

One ministry dominates both the count and the money. The Ministry of Road Transport and Highways runs 972 of the 1,862 projects, 52 per cent of the total, with a revised cost of ₹9.55 lakh crore, a quarter of the ₹38.11 lakh crore aggregate.

  • Road Transport and Highways: 972 projects, ₹9.55 lakh crore, 52 per cent of projects and 25 per cent of cost
  • Railways: 288 projects, ₹7.38 lakh crore, 15 per cent of projects and 19 per cent of cost
  • Power: 108 projects, ₹6.55 lakh crore
  • Petroleum and Natural Gas: 117 projects, ₹4.42 lakh crore
  • Housing and Urban Affairs: 50 projects, ₹3.44 lakh crore
  • Coal: 121 projects, ₹2.22 lakh crore, 7 per cent of projects and 6 per cent of cost
  • Water Resources, River Development and Ganga Rejuvenation: 33 projects, ₹1.93 lakh crore
  • All other ministries: 173 projects, ₹2.63 lakh crore, spread across higher education, civil aviation, steel, telecommunications, labour and employment, ports, shipping and waterways, health and family welfare, mines, the Department for Promotion of Industry and Internal Trade, and sports

Roads and railways together, at 1,260 projects, make up two-thirds of the monitored pipeline and ₹16.93 lakh crore, or about 44 per cent of the revised cost.

Advertisement

Where the Projects Sit on the Timeline

The ministry reads the spread as a pipeline with clusters at the two ends of the scale: projects between 0 and 20 per cent and projects between 81 and 100 per cent. That pattern describes a list with many freshly started jobs sitting alongside many that are close to finishing.

Money behaves differently at each end. In the 81 to 100 per cent band, work on the ground runs ahead of spending. In the early stages, spending runs ahead of visible work, because land, contracts and site mobilisation are paid for before anything is built.

Spending ratios across sectors show how uneven that is:

  • Water and sanitation: 69.95 per cent of ₹1.97 lakh crore spent
  • Transport and logistics: 50.64 per cent of ₹20.37 lakh crore, or ₹10.31 lakh crore
  • Communication: 48.78 per cent of ₹1.34 lakh crore, or ₹65,227 crore
  • Energy: 39.49 per cent
  • Within transport: shipping 66.14 per cent, logistics 56.36 per cent, aviation 54.06 per cent, roads 51.02 per cent, railways 50.51 per cent, urban public transport 49.07 per cent
  • Within energy: storage 83.75 per cent, oil and gas 50.17 per cent, electricity generation 33.51 per cent, transmission and distribution 27.56 per cent

Smaller slices of the list carry their own weight. The communication category holds 31 telecom projects worth ₹1.34 lakh crore. Social and commercial projects, covering education, healthcare, real estate and tourism, number 79 and cost ₹95,305 crore, with ₹38,563 crore spent, or 40.46 per cent. A further 151 projects worth ₹2.18 lakh crore sit in a residual category spanning coal, steel, metals and mining and construction, where ₹67,429 crore has been spent, or 30.95 per cent. Coal alone has 115 of those projects, worth ₹1.83 lakh crore.

Advertisement

What Finished in October and What Joined the List

Three projects were commissioned during the month:

  • A ₹4,445 crore transmission scheme to connect renewable energy zones in Karnataka, commissioned on 16 October, covering Phase II of Koppal II and Phase I of Gadag II
  • A corridor with six lanes on NH-66, built at ₹641.46 crore
  • The rebuilding of Coke Oven Batteries 7 and 8 at Bhilai Steel Plant by the Ministry of Steel at ₹884.1 crore, completed on 30 October

Another 38 projects entered the monitoring system in October through the ministry's PAIMANA platform. The Ministry of Road Transport and Highways added 23, the Ministry of Steel five, the Ministry of Power three, and the ministries of Petroleum and Natural Gas and Housing and Urban Affairs and the Department of Higher Education two each, with the Ministry of Railways adding one.

Among the additions are a highway with eight access controlled lanes joining Vadhavan Port to the junction at NH-48 at ₹4,464 crore, the widening to four lanes of the Badnawar, Petlawad, Thandla and Timarwani section of NH-752D in Madhya Pradesh at ₹3,842.41 crore, and two phases of the Ahmedabad Metro: Koteshwar Road to the airport at ₹2,169.04 crore and GIFT City to Shahpur at ₹1,067.35 crore.

Project records now move through the PAIMANA-PROJ platform, which tracks central projects of ₹150 crore and above across the 17 ministries. Nearly 80 per cent of project data is updated through API links between ministry systems rather than manual entry, the ministry said.

Advertisement

Finance Ministry Puts Cost Escalation Under the Scanner

Scrutiny of the numbers is tightening ahead of the Union budget for the financial year that ends in March 2028. The Finance Ministry has told ministries that a request for a larger budget allocation will not be cleared where a project costing above ₹5 crore has crossed a 10 per cent tolerance limit on cost, unless the request carries an explanation of what changed in the estimate, why approvals were delayed, where implementation snagged and when the project will now finish.

For projects run by central public sector enterprises, the trigger is a gap of more than 15 per cent between original and revised cost. Those companies must flag projects of ₹25 crore or more in their budget notes, with a threshold of ₹100 crore for firms running several projects at once, such as NTPC. Projects below ₹5 crore are reported on a consolidated basis, and projects financed with external aid are listed separately, showing how much comes through the budget and how much sits outside it. For work carried over from earlier years, ministries must give progress, estimated cost and money spent up to September 2026.

The push followed pre-budget meetings in which the Department of Expenditure found that several projects had cost revisions blamed on delays without adequate explanation. A senior official, speaking on condition of anonymity, set out the new condition:

Any request for the enhanced budgetary allocation where the cost escalation exceeds 10%, beyond tolerance limit, will require detailed explanation for change in cost estimate, reason for delay in approvals and any implementation bottlenecks and specific timelines.

The same official framed the change as a question of ownership inside government:

Also, this will ensure higher accountability on the department level, put greater responsibility on administrative departments to justify revised budgetary provisions and demonstrate the resources required to complete ongoing projects.

The Finance Ministry's note draws on an earlier cut of the ministry's data, citing ₹3.22 lakh crore of overruns across 1,853 projects above ₹150 crore as of 1 October. The October report, which closes the month, counts ₹3,28,452 crore across 1,862 projects.

The next monthly report, covering November 2026, is due on 28 December. Budget decisions for the coming financial year will follow, with the explanations now required feeding into the choice of which projects receive additional allocations and which are flagged for delays.

Advertisement

Key Points

  • 1,862 central infrastructure projects, each above ₹150 crore, are monitored across 17 ministries and departments
  • Original cost stands at ₹34,82,840 crore and revised cost at ₹38,11,292 crore, an overrun of ₹3,28,452 crore
  • ₹17.87 lakh crore has been spent, or 46.88 per cent of the revised cost
  • 649 projects are past 80 per cent physical progress and 326 are past 80 per cent financial completion
  • Transport and logistics holds 1,324 projects worth ₹20.37 lakh crore, energy holds 229 projects worth ₹11.31 lakh crore
  • Road Transport and Highways accounts for 972 projects and ₹9.55 lakh crore, a quarter of the total cost
  • The report does not state how many projects individually ran over budget
  • 38 projects joined the PAIMANA platform in October and three major projects were commissioned
  • The Finance Ministry will require explanations for overruns beyond 10 per cent on projects above ₹5 crore before approving higher allocations
  • The November report is scheduled for release on 28 December 2026