Vietnam Awards $397 Million Contract for North-South High-Speed Rail Design

14 Min Read
Vietnam Awards $397 Million Contract for North-South High-Speed Rail Design

From Blueprint to Engineering

Vietnam's Thang Long Project Management Board, the investor under the Ministry of Construction, has approved a consortium led by France's Systra to carry out surveys, feasibility study, front end engineering design and bidding documents for the North-South high-speed railway. The package, known as TV-02, has an approved bid price of VND10.2433 trillion, or $397.19 million, and a 30 month implementation period.

Contents
  1. From Blueprint to Engineering
  2. Who Is in the Winning Group
  3. What the Consortium Must Deliver
  4. Why the Route and Stations Matter
  5. Land Clearance, Resettlement and a New Law
  6. Dak Lak Shows the Scale of Moving People
  7. The Timeline From Bid to Construction
  8. South Korea's Diplomatic Push and Its Payoff
  9. What Changes for Contractors and Suppliers
  10. What Is Not Yet Decided
  11. Key Points

The board's approval, announced on November 22, selects eight companies: Systra; South Korea's Sambo Engineering, Yooshin Engineering and Korea National Railway; and Vietnam's Transport Engineering Design Inc. (TEDI), Southern Transport Engineering Design Joint Stock Company (TEDI South), Transport Investment and Construction Consultancy Joint Stock Company (TRICC) and Hoang Long Construction Consultancy Joint Stock Company.

The contract is one of the largest consultancy packages in the project's preparation. It covers the work that turns a 1,541 kilometer corridor between Hanoi and Ho Chi Minh City into a route with fixed stations, bridges, tunnels and technical standards. The line is planned as a new double track railway with a 1,435 millimeter gauge and a design speed of 350 kilometers per hour.

The contract does not yet take effect. The board must negotiate with the consortium, and the approval of bid results is not the same as a signed contract. The board has said it plans to complete the contract before the end of November. The approved price compares with an estimated package price of more than VND10.782 trillion. The consortium was the only bidder when bids closed at 9 a.m. on November 9, 2026.

For a project of this scale, the study phase is where cost, route and technology are locked in. A feasibility study tests whether the railway can be built and operated as planned, what land and equipment it needs, and how much it should cost. FEED, or front end engineering design, defines technical requirements and cost estimates before construction contracts are tendered. Those documents will shape the bids that follow for civil works, rolling stock and systems.

Advertisement

Who Is in the Winning Group

Systra, the French engineering consultancy, leads the group. Its partners bring a mix of railway design, engineering and public rail experience. Korea National Railway is South Korea's national rail infrastructure body; Sambo Engineering and Yooshin Engineering are private design and engineering firms. TEDI and its southern affiliate, TRICC and Hoang Long are Vietnamese design consultancies.

The lineup is the same one behind the design award covered on November 22, when Korea National Railway, Sambo and Yooshin joined SYSTRA and TEDI. The new contract follows an earlier Ineco consultancy deal signed in February 2026, when Spain's Ineco was brought in with Artelia and RCIC to study costs and technical standards. The TV-02 package is larger and covers the formal feasibility study, overall technical design and bidding documents.

Pham Huu Son, chairman of TEDI, said Vietnamese contractors would take a relatively large share of the work. He pointed to their experience on the Hanoi to Quang Ninh high-speed railway and the Ben Thanh to Can Gio line. That experience matters because the Vietnamese partners will need to work inside a consortium led by a foreign firm, absorb technical methods and carry out a substantial part of the surveys and design.

The contract uses a fixed unit price arrangement for survey work and a lump sum arrangement for the feasibility study, FEED design and bidding documents. That split matters: survey costs can change with ground conditions, while the design work has a defined scope and price. The 30 month clock starts when the contract takes effect, not when the bid result is approved.

Advertisement

What the Consortium Must Deliver

Within 12 months from the contract's effective date, the consortium must complete a mid-term feasibility study report. The route must be stable enough to fix the main control points: station locations, bridges and tunnels. The report must also present technology options for the government to review, appraise and decide. The route and design must meet technical standards while fitting local development plans and limiting disruption to residents.

After about 15 to 18 months, component projects that meet conditions will be studied and proposed for faster procedures, with the aim of early commencement. The two terminal stations are a priority. Ngoc Hoi Station in Hanoi and Thu Thiem Station in Ho Chi Minh City are expected to be built by the end of 2027 or early 2028. Their design is tied to connections with urban rail networks and to city development plans built around public transport.

The technical baseline is already fixed in broad terms. The line is planned for 23 passenger stations and five freight stations. It will use electrified rail technology and carry passengers, with the ability to move freight when needed and to serve defense and security needs. The design load is 22.5 tons per axle, a measure of the weight each axle puts on the track. That figure affects bridge strength, track design and the kinds of trains the line can carry.

Advertisement

Why the Route and Stations Matter

The corridor runs from Ngoc Hoi in Hanoi to Thu Thiem in Ho Chi Minh City and is meant to cut the journey from roughly 30 hours to about five. Gauge is the distance between the rails, and 1,435 millimeters is the standard used by many mainline railways. Design speed is the speed engineers use to set curves, gradients and signaling, not a promise of everyday running speed.

The National Assembly resolution lists 20 provinces and centrally run cities along the route. The project board's current summary names 15, after Vietnam's 2025 reorganization of provincial boundaries. The current list includes Hanoi, Ninh Binh, Thanh Hoa, Nghe An, Ha Tinh, Quang Tri, Hue, Da Nang, Quang Ngai, Gia Lai, Dak Lak, Khanh Hoa, Lam Dong, Dong Nai and Ho Chi Minh City.

Earlier descriptions of the project used about $65 billion; the formal preliminary figure is VND1,713.548 trillion. The dong figure is the formal preliminary investment. Dollar equivalents in project documents range from about $66.44 billion to $67.34 billion. The project is public investment, funded from the state budget through medium term public investment plans and other lawful capital. That financing structure makes the feasibility study more than an engineering exercise: it sets the cost base that the government must budget for over the 2025 to 2035 implementation period.

Advertisement

Land Clearance, Resettlement and a New Law

Land is the part of the project that will touch households before any train runs. The preliminary land requirement is about 10,827 hectares: about 3,655 hectares of rice land, 2,567 hectares of forestry land and 4,605 hectares of other land. The preliminary number of resettled residents is about 120,836.

The schedule ties land work to the design. For sections where the route is clear, the project board and the consultant will report to the Ministry of Construction so that land clearance stakes can be placed. The stakes then go to local authorities. The goal is to hand over the stakes within three months of the mid-term report's approval, expected in the fourth quarter of 2027. Land clearance is planned for completion in the fourth quarter of 2028, under separate projects led by provincial People's Committees.

The National Assembly passed changes to the land law on Saturday that allow expropriation for selected special projects, a move meant to speed site clearance. Expropriation is the compulsory purchase of private land for public use, with compensation set under the law. The same session set a target of at least 10 percent economic growth this year. For the railway, the legal change could shorten the time between a fixed route and construction, though the project still depends on resettlement areas, compensation and local implementation.

Advertisement

Dak Lak Shows the Scale of Moving People

Dak Lak province, one of the localities on the route, announced on November 16 that it plans 18 resettlement areas and five sites for relocating cemeteries. It estimates about 3,025 households will need to be relocated along the main line section. Construction of the Hoa Kien resettlement area began in late October. The province aims to start work in December on the remaining sites that meet the requirements.

The numbers show why land clearance is being treated as a separate project. A railway route can be fixed on a map in months, but moving households, compensating for land and building new settlements takes local administration, budget and time. The 120,836 figure for resettled residents across the line is preliminary. The final count will depend on the approved alignment, station locations and detailed measurement.

Advertisement

The Timeline From Bid to Construction

The project has several dates that will determine when construction can begin. The National Assembly approved the investment policy in Resolution 172/2024/QH15 on November 30, 2024. The government adopted an implementing resolution on April 6, 2025 for compensation, support and resettlement as a separate project. The government's implementation plan, Resolution 106/NQ-CP, signed by Prime Minister Pham Minh Chinh on April 23, 2025, set out the tasks for ministries and localities.

  • November 30, 2024: National Assembly approves investment policy in Resolution 172/2024/QH15.
  • April 6, 2025: Government adopts resolution for compensation, support and resettlement as a separate project.
  • April 23, 2025: Government issues Resolution 106/NQ-CP to implement the investment policy.
  • November 9, 2026: Bids close for package TV-02 at 9 a.m.; the consortium is the only bidder.
  • November 22, 2026: Thang Long Project Management Board approves the contractor selection result.
  • Late November 2026: Board plans to complete negotiations and sign the contract.
  • Within 12 months of contract start: Mid-term feasibility study report due with route, control points and technology options.
  • Late 2027: Mid-term report approval targeted; construction start targeted for December 2027.
  • Fourth quarter 2028: Land clearance scheduled for completion.
  • 2035: Project aims to be basically complete.

The construction start has slipped by one year to the end of 2027, after Vietnam said in September that progress had lagged expectations. The Ministry of Construction is striving to begin construction in December 2027. The schedule from the fourth quarter of 2026 to the fourth quarter of 2028 covers preparation, appraisal and approval of the feasibility study and the start of construction.

The next checkpoint is the mid-term report. Its approval would allow land clearance stakes to move to localities within about three months. A delay there would push the land work and the construction start. The contract's 30 month term means the main design work is meant to run into 2029, even as early construction is targeted for late 2027. That overlap is built into the plan: some sections and terminal stations are meant to move first while design continues elsewhere.

South Korea's Diplomatic Push and Its Payoff

South Korea's government treated the contract as a strategic win. The contract is worth about 560 billion won and is the largest overseas railway planning and design contract won with Korean institutions and companies taking part. Government support included summit diplomacy, meetings at minister and vice minister levels, a bid support team led by the second vice minister in June, and a visit by the then minister in July with a personal letter from the president. The leaders discussed high-speed rail cooperation during talks in August last year and April this year.

Hong Ji-seon, South Korea's Minister of Land, Infrastructure and Transport, said the result combined public and private capacity with sustained government effort. He also set out the later goal: to help Korean firms compete for construction, rolling stock and operations.

This contract win is an achievement made possible by combining the capabilities of public institutions and private companies with the government's sustained efforts," Hong said. "We will actively support Korean companies so they can demonstrate their competitiveness in follow-up projects, including the main Vietnam North-South express railway project.

For Korean firms, the design phase is a doorway. A company that helps set the route, station locations and technical standards gains knowledge that is useful when the main construction and rolling stock contracts are tendered. The same logic applies to Systra and the Vietnamese partners. The contract value is small compared with the $67 billion project, but the work defines the packages that follow.

Advertisement

What Changes for Contractors and Suppliers

The award gives engineering firms, rail suppliers and construction companies a clearer view of the project's shape. The route, station locations and technical standards will be fixed through the feasibility study and FEED. Those decisions determine how much track, signaling, electrification, rolling stock and station construction will be needed, and when the work will be tendered.

The project is still preconstruction. No main civil works contract has been awarded. The design work will produce the bidding documents that let the government tender those contracts. For suppliers, the timing matters: early station work at Ngoc Hoi and Thu Thiem is targeted for late 2027 or early 2028, while the full line is meant to be basically complete in 2035.

The package also sets a template for how Vietnam will use foreign and domestic consultants. The lead is foreign, the project owner is a state body, and four Vietnamese firms are inside the consortium. That structure is meant to bring international railway experience into Vietnamese design practice while giving local firms a larger role than in a pure foreign consultancy contract. Clarity on route, design and bidding turns a $67 billion headline into timed cash flows across engineering, rolling stock and land services, with late 2027 as the next key checkpoint.

What Is Not Yet Decided

The exact contract signing date has not been announced. The board approved the selection result and plans to finish negotiations before the end of November, but the contract takes effect only after signature. The final route, station locations and technology choice still need to pass the feasibility study and government approval. The mid-term report is the point where those choices become formal proposals.

The final cost and final land take are also not fixed. The preliminary investment is VND1,713.548 trillion, and the preliminary land use is about 10,827 hectares with about 120,836 resettled residents. Detailed surveys, design and compensation work will change those figures. The number of households in Dak Lak alone, about 3,025 along the main line section, shows how local details can add up across 15 or 20 localities.

The construction start target is December 2027, but the project has already slipped once. The land clearance completion target is the fourth quarter of 2028. The feasibility study approval, expected in the fourth quarter of 2027, is the next formal checkpoint. If it holds, land stakes can move to localities within about three months and early works can follow.

Key Points

  • Vietnam's Thang Long Project Management Board approved a Systra-led consortium for package TV-02 on the North-South high-speed railway.
  • The contract is worth VND10.2433 trillion ($397.19 million) and runs 30 months, covering surveys, feasibility study, FEED design and bidding documents.
  • The consortium includes Systra, Sambo Engineering, Yooshin Engineering, Korea National Railway, TEDI, TEDI South, TRICC and Hoang Long.
  • The 1,541 kilometer line is planned to link Ngoc Hoi Station in Hanoi with Thu Thiem Station in Ho Chi Minh City at a design speed of 350 km/h.
  • The preliminary total investment is VND1,713.548 trillion, with dollar equivalents of about $66.44 billion to $67.34 billion in project documents.
  • About 10,827 hectares of land and about 120,836 resettled residents are estimated in the preliminary plan.
  • The mid-term feasibility report is due within 12 months of the contract start, with approval targeted for the fourth quarter of 2027.
  • Construction is targeted for December 2027, land clearance for the fourth quarter of 2028 and basic completion for 2035.
  • South Korea's government cited the contract as its largest overseas railway planning and design win involving Korean institutions and companies.