China to Audit 17 Automakers as Supplier Payment Pledges Face Annual Checks

11 Min Read
China to Audit 17 Automakers as Supplier Payment Pledges Face Annual Checks

Supplier checks will test whether the money arrives on time

China will check the supplier payment practices of 17 major automakers through annual assessments, public results and random checks involving at least 15 suppliers per manufacturer, turning promises to pay within 60 days into a recurring compliance test.

Contents
  1. Supplier checks will test whether the money arrives on time
  2. From a public pledge to a published assessment
  3. What will inspectors examine?
  4. When does the payment clock start?
  5. Smaller suppliers receive stronger protection
  6. Cash, bank bills and the cost of waiting
  7. Price negotiations cannot leave suppliers unpaid
  8. Progress is visible, but the measures tell different stories
  9. Who carries the financing burden?
  10. Key Points

The China Association of Automobile Manufacturers (CAAM) announced the assessment arrangements on November 16, 2026. Commissioned by the Ministry of Industry and Information Technology (MIIT), the association will examine payment deadlines, payment methods, purchasing contracts and what happens when suppliers deliver parts before a final price is agreed.

The companies covered include BYD, Nio, Xiaomi, Seres, Xpeng and Li Auto, alongside established manufacturers including FAW, SAIC, Dongfeng, Changan, BAIC, GAC and Geely. The first assessment will draw on reports covering 2026 and its fourth quarter, due to the ministry by January 31, 2027.

The central issue is how long suppliers actually wait for usable money. A promise to pay within 60 days offers limited relief if inspections take too long, accounting procedures delay the starting date, or a supplier receives a promise of future payment while needing cash for wages and materials today.

The new checks follow government rules that set inspection deadlines of three or five working days, encourage payment to smaller suppliers within 30 days, and require partial payments while prices are being negotiated. Together, those measures address the steps between delivering a component and receiving payment.

From a public pledge to a published assessment

Seventeen major automakers publicly committed in June 2025 to payment periods of no more than 60 days. CAAM subsequently issued its supplier payment initiative on September 15, 2025. The government has since moved toward a system combining company reports, independent assessment and official inspections.

The main developments are:

  • June 2025: Seventeen automakers pledged to limit supplier payment periods to 60 days.
  • September 15, 2025: CAAM issued its industry initiative on supplier payments.
  • September 2, 2026: The general offices of MIIT and the State Administration for Market Regulation issued detailed payment management rules, published on September 7.
  • November 16, 2026: CAAM announced how the annual assessments would work.
  • January 31, 2027: Reports covering 2026 and its fourth quarter are due for the first assessment.
Advertisement

The ministries' supplier payment notice, numbered 工信厅联通装函〔2026〕424号, draws on the Anti-Unfair Competition Law, the Anti-Monopoly Law and the Regulations on Ensuring Payments to Small and Medium-sized Enterprises.

Automakers must submit annual payment reports by January 31 and reports covering the first half of each year by July 31. The assessment itself will take place once a year. No date has been announced for publication of the first results.

What will inspectors examine?

CAAM will assess purchase orders accepted as meeting requirements during the evaluation period. Automakers will submit information, a dedicated team will verify it, experts will review the findings and the results will be made public.

Each manufacturer will face random checks involving at least 15 suppliers. Document checks and visits to suppliers will help establish whether the figures submitted by the automaker match suppliers' experience. Across 17 manufacturers, that means at least 255 supplier checks, although some suppliers may serve several manufacturers.

The assessment has four main areas: payment management systems, payments to small and medium-sized enterprises (SMEs), payments to larger suppliers, and arrangements during price negotiations. Inspectors will also examine digital systems and whether each supply contract lasts at least one year.

For SMEs, the review will check whether payment periods stay within 60 days. It will separately examine whether payments are entirely in cash and whether they are entirely through cash and bank acceptance bills. For larger suppliers, it will check the 60 day commitment and whether cash and bank acceptance bills together account for at least 80% of payments.

Those separate measures matter because payment speed and payment form affect suppliers differently. A company may meet an agreed deadline by issuing an accepted bill, while the supplier still waits for the date when that bill can be redeemed for its full value.

When does the payment clock start?

The September rules say the payment period begins when goods, work or services have been delivered and accepted. Acceptance is the buyer's confirmation that the delivery meets the agreed requirements.

MIIT explained in its official policy explanation that manufacturers had used different starting points, including delivery acceptance, centralized account reconciliation, invoice receipt and vehicle installation checks. Lengthy or unclear acceptance procedures had extended suppliers' actual waiting times.

Advertisement

The written notice sets precise limits. Manufacturers should receive production materials in the agreed quantity within one working day of the scheduled delivery, using logistics records to establish timing. General production materials, including ordinary components, must be inspected within three working days of receipt. If that deadline passes without inspection, the goods are treated as accepted.

Components that genuinely require installation in a vehicle must complete inspection when the vehicle comes off the production line within five working days of receipt. Rejected materials are handled under the contract's responsibility and compensation provisions, and their value is excluded from accounts payable.

Frequent deliveries receive special treatment. Where suppliers deliver at least twice a month, the parties may agree on a continuous supply cycle, normally no longer than a month. The payment limit runs from the midpoint of that cycle to payment, preventing a manufacturer from starting the clock only after its monthly reconciliation is complete.

Smaller suppliers receive stronger protection

Small and medium-sized suppliers are encouraged to receive payment within 30 days of goods being accepted, with 60 days as the maximum. The government also encourages manufacturers to pay these businesses entirely in cash, including bank transfers and wire transfers.

Contracts that leave the payment method unspecified carry a firmer requirement: manufacturers must pay SME suppliers in cash. Commercial bills or electronic certificates recording money owed cannot substitute for cash in those circumstances.

Large automotive groups and their wholly owned or controlled subsidiaries are also encouraged to pay SMEs in cash within 60 days of delivery for goods, construction work and services. This broader delivery based approach would give suppliers greater certainty across different types of purchasing.

Automakers must improve their internal controls and press subsidiaries and suppliers of major assemblies to pay smaller businesses promptly. The ministry has identified differences among subsidiaries and branches as one reason that improvements announced by a parent company may not reach every supplier.

SME status can itself become a point of disagreement. The notice directs businesses to the ministry's company size assessment service and allows disputes to be referred to the responsible local government department where the business claiming SME status is located.

Cash, bank bills and the cost of waiting

The September notice encourages cash or bank acceptance bills and prohibits forcing suppliers to accept commercial acceptance bills or supply chain bills. A bank acceptance bill carries a bank's promise to pay at maturity; a commercial acceptance bill relies on the company responsible for payment.

Advertisement

A supplier needing money before a bill matures may sell it at a discount. The amount lost is a financing cost. The rules require contracts using such instruments to specify who bears that cost and call for reasonable limits on their use.

The written notice counts payment timing from a cash transfer or the issuance of a bank acceptance bill or another eligible instrument. MIIT's accompanying explanation describes cash transfer timing as the general reference and gives broader guidance against forcing suppliers to accept noncash methods. The assessment's separate cash and bill measures will therefore be important in showing how suppliers are paid.

Manufacturers that miss contractual deadlines must pay interest under the applicable law. For SME suppliers, the notice specifically refers to Article 17 of the Regulations on Ensuring Payments to Small and Medium-sized Enterprises.

The notice also addresses exceptions. An automaker facing genuine financial difficulty should communicate early and arrange any delay according to the contract, but that provision excludes SME suppliers. If a supplier submits a compliant invoice late, payment may be postponed by the corresponding delay.

Price negotiations cannot leave suppliers unpaid

Suppliers sometimes continue delivering parts while negotiating a new price. The assessment will examine whether contracts provide for payments during that period, so an unresolved price does not leave the entire bill outstanding.

For continuous supply, the benchmark is an advance payment of at least 90% of the most recent effective contract price. For supply that is not continuous, the benchmark is at least 70% of the industry average price or the price agreed when the supplier was selected for development.

The parties must settle the difference once the final price is agreed. A supplier can then receive the balance, or return an excess payment, rather than financing the full delivery throughout negotiations.

The September notice also prohibits manufacturers from using shorter payment periods as a reason to demand lower supply prices. It calls for fair contracts and says price demands must take account of production costs and hidden quality or safety risks.

CAAM has identified cases in which companies sought price reductions or attached extra conditions while shortening payment terms. Assessing both prices and payment arrangements addresses the practical tradeoff suppliers can face: receiving money sooner while being asked to accept less for the same goods.

Progress is visible, but the measures tell different stories

CAAM's recent survey put the average payment period at about 54 days, roughly 10 days shorter than a year earlier. Four manufacturers averaged fewer than 50 days. Fourteen introduced additional preferences for SMEs, two paid SME suppliers entirely in cash, and five allowed businesses under financial pressure to apply for early payment.

Advertisement

Manufacturers have also changed internal procedures. Some moved from monthly settlement to settlement every 10 days, installed automatic payment systems or shifted the starting point from accounting entry to delivery and acceptance. Some companies set aside more than 10 billion yuan for supplier payment arrangements.

A financial statement analysis covering 14 automakers found a different trend: average turnover periods for accounts payable and notes payable increased from 164.4 days at the end of 2025 to 187.5 days in the first half of 2026, a rise of 23.1 days.

The two measures track different things. CAAM's reported payment measure uses an acceptance to payment interval, described in the financial analysis as beginning at invoice acceptance and including certain bank bills. The financial statement calculation relates outstanding trade debts and bills to the cost of goods sold. Inventory, outstanding bills and the timing of accounting entries affect that calculation.

The new assessment brings several of those moving parts into the same review: acceptance dates, deadlines, payment instruments and outstanding balances. That will give suppliers and regulators a more detailed picture than a single average payment figure.

Who carries the financing burden?

Cao Yuanyuan, director general of the People's Bank of China's Financial Market Department, said at a September 14 government briefing that delayed payments by large companies can force smaller suppliers to borrow to keep operating. In practical terms, the supplier pays financing costs while waiting for money already earned.

The scale extends beyond automobiles. Outstanding electronic payment certificates stood at 2.4 trillion yuan in July 2026, down from a peak of 3 trillion yuan, according to central bank figures. Their average payment period was 92 days. Large industrial companies held 29.77 trillion yuan in accounts receivable at the end of September, up 10% from a year earlier, with an average collection period of about 72 days.

MIIT and other authorities will summon automakers with large unpaid balances, deliberately extended payment periods or frequent complaints for talks and press them to correct problems. Violations of laws and regulations can lead to penalties.

Suppliers can submit payment problems through the ministry's online reporting mechanism. Challenges to published assessment results go first to the assessing institution for review; complaints about the assessment process itself go to MIIT for investigation. The ministry says it will track payment trends and adjust policy as practical problems emerge.

For suppliers, the immediate change is a route from a payment promise to a checkable record: when goods arrived, when they were accepted, what was paid and whether receiving that payment carried an extra cost.

Key Points

  • CAAM will assess 17 major automakers annually, checking at least 15 suppliers per manufacturer.
  • Reports covering 2026 and its fourth quarter are due by January 31, 2027.
  • Ordinary production materials must be inspected within three working days; missing that deadline counts as acceptance.
  • SME suppliers are encouraged to be paid within 30 days, with a maximum of 60 days.
  • Payments during price negotiations generally must reach at least 90% for continuous supply or 70% for other supply.
  • Results will be public, and manufacturers with serious payment problems face official talks and demands for correction.
Share This Article