The Grant Clock Keeps Ticking in Kathmandu
Nepal's Finance Ministry has held a request from the Millennium Challenge Account Nepal for more than six months, leaving two infrastructure projects without the extra time their managers say they need. MCA-Nepal sent the request in mid May 2026, asking the ministry to formally approach the Millennium Challenge Corporation for a one year extension of the compact due to end on August 30, 2028.
Contents
- The Grant Clock Keeps Ticking in Kathmandu
- What MCA-Nepal Wants Nepali Ministers to Approve
- What the Official Funding Papers Show
- Why a One Year Extension Is Legally Possible
- What Stopped the Work
- Why the Freeze Shook Nepal's Budget Planners
- The Transmission Line Has Its Own Delays
- Road Works Offer a Contrast
- Old Political Arguments Still Shape the File
- Why Kathmandu Has Not Moved Faster
- A Short Timeline of the Delay
- What Happens Next and What Is Still Unknown
- Why the August 2028 Deadline Matters
- Key Points
The stakes are concrete. The programme covers a 315 kilometre, 400 kV transmission line and upgrades to roads, including a section of the Mahendra Highway. The headline value is $747 million: $550 million in MCC investment and $197 million from Nepal, according to the funding plan in the First Amendment published by the US Department of State.
An MCA-Nepal official involved in implementation said ministry officials had signalled support in conversations but had not turned that support into a decision. The official said:
In informal conversations, ministry officials say they are positive about extending the term, but that has yet to translate into a decision.
What MCA-Nepal Wants Nepali Ministers to Approve
MCA-Nepal's request asks the Finance Ministry to speak for Nepal to MCC headquarters. Under the compact, the ministry is the liaison body, and the finance secretary chairs the MCA-Nepal board. The Cabinet must endorse the extension before Nepal can send the formal request to MCC. Officials say the matter has been taken to the Prime Minister's Office, but no decision has been announced.
A senior MCA-Nepal board member, who is not authorised to speak to the media, said the agency framed the request as a repair to the project schedule. By August 2026, the board member said three months had passed since the letter went to the ministry without clear information on the term extension.
A senior Finance Ministry official said the letter was under consideration. The official said:
There should be no issue with extending the grant project. I believe the political leadership is also positive about it.
What the Official Funding Papers Show
The State Department filing, Treaties and Other International Acts Series 25-1119, says the First Amendment was signed in Washington and Kathmandu on September 22 and November 19, 2025, and entered into force on November 19, 2025. It raised the Program Funding ceiling by $50 million to $525,977,559.41. Nepal's Council of Ministers approved Nepal's signature.
The amendment says the reason for the increase was that the cost to complete the Electricity Transmission Project had risen above its budget. The original compact, signed September 14, 2017, set Program Funding at $459.5 million and a Compact CDF of $40.5 million. A Compact CDF is money used to help carry out the programme rather than money for construction itself. Public descriptions in Nepal have also used September 15 as the signing date.
On June 28, 2024, MCC reallocated US$16,477,559.41 of excess implementation money to Program Funding, taking that line to US$475,977,559.41 before the $50 million increase. The revised table totals $550 million in MCC investment, $197 million from Nepal and a $747 million grand total, including about $286.749 million for transmission lines and $52.285 million for the road project overall.
Nepal's contribution rose from an early $150 million figure to $197 million, which explains why older descriptions of the compact used $697 million before the extra $50 million. Frank Sellin, a spokesperson for the U.S. Embassy in Kathmandu, described the American contribution as about $600 million overall, with $550 million approved so far. The amendment's table totals $550 million in MCC investment.
Why a One Year Extension Is Legally Possible
The extension route exists in United States law. Sellin said the provision was approved by both chambers of Congress and signed into law by Donald Trump in November 2025. It allows a one year extension for MCC compact projects in Nepal, Indonesia, Kosovo and Senegal, subject to available resources. It also requires the relevant congressional committee to be informed before an extension is granted.
Nepal still has to approve the change for it to take effect. The request points to an early January Senate vote, while the embassy says the legal authority came from the November 2025 law signed by Trump. Sellin said MCC told Nepal's Finance Ministry about the possibility of negotiating an extension before the public announcement.
An MCA-Nepal official familiar with headquarters communication said MCC viewed the request favourably because the reasons were well founded and because the law covers projects in four countries. The official said MCC headquarters had been positive about the proposal.
What Stopped the Work
MCA-Nepal's letter to the Finance Ministry cites what it calls unavoidable circumstances. It says Trump's decision in July 2025 to pause foreign assistance and halt MCC payments left the projects uncertain for months before MCC operations, including in Nepal, resumed. Official statements from the earlier period give a related sequence: an executive order on January 20, 2025 began a 90 day pause, MCC emailed Nepal on February 14 that compact payments were halted, and the US Embassy said disbursements were paused under the order and Office of Management and Budget guidance.
Frank Sellin, the U.S. Embassy spokesperson, said the compact itself remained in force through that period. He said:
MCC Compact was never halted in 2025 or at any time since it entered into force.
Sellin said Nepal's compact received an exception after the temporary pause. When the freeze first became public, an MCA-Nepal official said staff were reporting to work but money was not moving. The official said:
We are working as usual and there have been no changes such as fund cuts or staff layoffs. However, payments after January 20 have not been made, and new procurements have been halted.
Why the Freeze Shook Nepal's Budget Planners
Surendra Pandey, a former finance minister, said the pause created risks Nepal could not quickly absorb. He said:
Do we have the capacity to take the MCC to court? Or can we continue the projects with our own resources?
Pandey said stopping a contract process could bring fines, while land acquisition remained a legal duty already under way. He said:
Neither Europe, India, nor China is going to fill that vacuum, and nor do we have the financial wherewithal to invest or give continuity to these projects on our own. We were not prepared.
Akhilesh Upadhyay, a senior fellow at the Centre for Strategic Affairs at IIDS, a Kathmandu think tank, called MCC the biggest infrastructure grant in Nepal's history. He said:
How does Nepal now address its investment needs?
Upadhyay also pointed to United States support for health, including malaria eradication, vaccination programmes and HIV/AIDS treatment, and to past American advocacy for human rights, democratic values and inclusion. Former Finance Secretary Rameshore Khanal expected the grants to resume. He said:
I hope the US government will resume the operation of investment instruments as they have no basis to stop the [MCC] compact process.
Finance ministry officials at the time said no review of the United States aid shift had been completed. The present extension request now sits with that same ministry.
The Transmission Line Has Its Own Delays
The transmission line has problems that started before the funding pause. In October 2023, MCA-Nepal cancelled bids for the 315 kilometre, 400 kV line after every bidder quoted prices far above the estimated cost. A tender for a 297 kilometre line was re-launched in November 2024, with bids due January 30. MCA-Nepal says a fresh contract took almost nine months to award.
The line is intended to run from Ratmate in Nuwakot to Butwal and onward to Gorakhpur. A 400 kV line is a high voltage backbone that moves large amounts of electricity over long distances, much like a motorway carries heavy traffic. The compact describes the electricity project as a way to support power trade and improve the reliability of Nepal's grid.
Land is the stubborn obstacle. Officials say compensation has been distributed for only 18 km of the transmission line's right of way, compared with a line of 315 km, even though a large team and resources have been mobilised. An official who monitors the MCC projects from the centre and the field said contractors cannot do much without cleared sites. The official said:
How can contractors start work until they get the site clearance?
Other concerns include land acquisition, compensation, construction quality, compliance with environmental rules and quality issues at substations. An official familiar with compensation work said the level paid under MCC could be hard for future projects to match. The official said:
The way compensation is being provided to affected families and land owners under the MCC project could create problems for future transmission line projects. We may not be able to afford similar levels of compensation in other projects.
Road Works Offer a Contrast
The road component has been smoother. MCA-Nepal officials say the road upgrade is progressing well while the transmission line absorbs most attention. The works include upgrading five road sections, among them a section of the Mahendra Highway. The official funding table assigns $42.451 million to strategic road maintenance works, $9.833 million to technical assistance and $52.285 million to the road project overall.
The road works matter to ordinary users because better surfaces and maintenance can shorten travel times and reduce vehicle damage. For the compact as a whole, the road component gives Nepal a visible deliverable while the power line faces land and procurement delays.
Old Political Arguments Still Shape the File
The MCC compact was divisive before work began. Critics argued that some provisions undermined Nepal's sovereignty, and the agreement won ratification in the House of Representatives only in February 2022, with the date recorded as February 27. It entered into force on August 30, 2023.
That history helps explain why officials speak carefully in public even when they sound supportive in private. Finance Ministry officials have taken the request to the Prime Minister's Office, yet no public decision has been made.
Why Kathmandu Has Not Moved Faster
The delay is political and procedural. The Finance Ministry must forward the request to MCC, but the Cabinet has to endorse it first. The US Embassy in Kathmandu and senior MCA-Nepal officials have raised the issue with Finance Minister Swarnim Wagle and senior ministry officials.
A second finance official said the request was still under discussion and had not been forwarded to MCC headquarters. The official said:
It is still under discussion.
That official did not say when the ministry would act. Until a decision is made, MCA-Nepal cannot use the extra year even if MCC headquarters is willing.
A Short Timeline of the Delay
The sequence matters because each step adds a gate that Nepal must open before the extension can reach Washington.
- September 14, 2017: Nepal and the United States signed the original compact.
- February 27, 2022: Nepal's House of Representatives ratified it after intense controversy.
- August 30, 2023: The compact entered into force, starting a five year implementation clock that ends August 30, 2028.
- October 2023: MCA-Nepal cancelled transmission line bids after prices came in far above estimates.
- June 28, 2024: MCC reallocated US$16,477,559.41 from excess implementation money to Program Funding.
- January 20, 2025: Trump ordered a 90 day pause on much United States foreign assistance. The embassy later said the Nepal compact received an exception and was never halted.
- February 14, 2025: MCC emailed Nepal that compact payments were halted during the review, according to the Finance Ministry statement from that time.
- September 22 and November 19, 2025: The First Amendment was signed, and it entered into force on November 19 with a $50 million increase.
- November 2025: Congress approved and Trump signed the law allowing one year extensions for MCC projects in four countries.
- Mid May 2026: MCA-Nepal asked the Finance Ministry to seek an extension from MCC.
No Cabinet date, forwarding date or MCC decision date has been announced.
What Happens Next and What Is Still Unknown
Nepal's Cabinet has no announced date for a decision. No date has been set for forwarding the request to MCC, and MCC has not granted an extension. Once the request is forwarded, MCC headquarters will review the reasons cited by MCA-Nepal and decide whether to grant the extra year. The United States law also requires notice to the relevant congressional committee.
Implementation problems remain unresolved. No date has been given for completing land acquisition, paying all compensation, clearing sites, resolving substation quality concerns or finishing environmental compliance work. The government has not said how it will handle contractor schedules if the compact ends on August 30, 2028 without an extension.
Why the August 2028 Deadline Matters
MCA-Nepal says implementation has slipped by about 14 months because of the funding disruption and the need to restart the transmission line tender. If approved, the extension would give the agency one more year beyond August 30, 2028. Officials say an early decision would help maintain momentum and ease pressure as the deadline approaches.
Another MCA-Nepal official said the deadline is tight even though just over two years remain. The official said:
Without an extension, neither of the two projects undertaken by MCA-Nepal will be completed by the August 2028 deadline.
For communities along the line and the roads, the dispute is concrete. It affects when land compensation is paid, when contractors enter sites, when substations are finished and when Nepal can use a new high voltage route for electricity trade. MCA-Nepal officials argue that, in a country where development projects often run late, an added year is practical if it helps finish the compact.
Key Points
- MCA-Nepal asked the Finance Ministry in mid May 2026 for a one year extension of the $747 million MCC compact.
- The Cabinet must endorse the request before the ministry can formally approach MCC headquarters.
- The compact is due to end on August 30, 2028, and MCA-Nepal says implementation has slipped by about 14 months.
- Official funding papers show a $50 million increase to cover rising electricity transmission costs.
- United States law allows a one year extension for MCC projects in Nepal, Indonesia, Kosovo and Senegal, subject to resources and congressional notice.
- Land acquisition, compensation, procurement, environmental compliance and substation quality remain key obstacles.
- No date has been announced for a Cabinet decision, a formal request to MCC or an extension ruling.