A 349 km project with a tightly defined funding package
Vietnam has capped central budget funding at 61.394 trillion dong for the main expressway line of Ring Road 5 in the Hanoi Capital Region during the 2026 to 2030 period. The money is assigned to about 116 km crossing Hai Phong, Bac Ninh, Ninh Binh and Hung Yen. Construction is scheduled to begin in September 2027, with substantial completion in 2030 and operation starting in 2031.
Contents
- A 349 km project with a tightly defined funding package
- A construction budget with clear exclusions
- The dates that now govern the project
- Who will approve and coordinate the work
- How funding is meant to keep pace with construction
- Where private investment could fit
- Land, side roads and daily life along the route
- The agencies clearing physical and regulatory obstacles
- Materials, power lines and the 2031 opening target
- Key Points
The instruction appears in Government Resolution 406/NQ-CP, signed on 24 November 2026 by Permanent Deputy Prime Minister Pham Gia Tuc on behalf of the government. It implements National Assembly Resolution 38/2026/QH16, dated 24 August 2026, which approved the investment policy for the entire project.
The full undertaking is much larger than the section covered by this central allocation. Ring Road 5 is planned to run for about 349 km through seven provincial and municipal jurisdictions: Hanoi, Ninh Binh, Hung Yen, Hai Phong, Bac Ninh, Thai Nguyen and Phu Tho. Its preliminary total investment is approximately 288.268 trillion dong, and the project has been approved under the public investment form.
The stated objective is to create an expressway connecting Hanoi with other localities in the region, meet demand for sustainable transport, spread development momentum and open new space for economic growth. The implementation resolution turns that objective into assigned budgets, feasibility studies and deadlines, with the work divided into component projects rather than managed as a single undifferentiated construction task.
A construction budget with clear exclusions
The 116 km expressway programme represents about 33.2% of the full route length, based on the approximate figures of 116 km and 349 km. The central funding ceiling of 61.394 trillion dong is equivalent to about 21.3% of the preliminary total investment of 288.268 trillion dong. Distance and money therefore describe different things: one measures the physical scope of the initial construction programme, while the other compares its central allocation with the estimated cost of the entire undertaking.
The central sum is a ceiling, meaning the amount arranged under this provision can be lower but cannot exceed 61.394 trillion dong. It is reserved for the main expressway line. It cannot be used for compensation, support or resettlement, and it cannot finance the construction of parallel roads.
Local budgets have a separate set of responsibilities. The People's Committees of Hanoi, Hai Phong, Bac Ninh, Ninh Binh, Hung Yen, Thai Nguyen and Phu Tho must arrange local money for land recovery, compensation, support, resettlement and the parallel roads. Land recovery is the administrative process through which land is taken back for a public project, while compensation and resettlement concern the financial and practical arrangements made for affected people.
A parallel road is a side road running alongside the expressway. It gives local journeys a separate route instead of requiring every short trip to use the main expressway. Hai Phong, Bac Ninh, Ninh Binh and Hung Yen have been told to prioritize the sections needed for safe and convenient local traffic when the portion of the expressway funded during 2026 to 2030 enters service. Their central construction allocation and these local expenses must consequently be planned together, even though the money comes from different budgets.
The dates that now govern the project
The government has attached a sequence of approvals, construction milestones and opening targets to the funding decision. The schedule also distinguishes the first 116 km expressway programme from the remaining components of the 349 km route.
- 24 August 2026: The National Assembly issues Resolution 38/2026/QH16, approving the investment policy for Ring Road 5.
- 24 November 2026: Permanent Deputy Prime Minister Pham Gia Tuc signs Government Resolution 406/NQ-CP. Investment preparation is placed in 2026, with project implementation beginning in 2027.
- Second quarter of 2027: Preparation, verification, appraisal and approval of the component projects for the 116 km expressway programme must be completed.
- Before September 2027: The Ministry of Industry and Trade must issue a mechanism for coordinating construction materials across regions and provinces.
- September 2027: Construction of the first expressway components is scheduled to start after the remaining preparatory work is completed.
- 2030: The 116 km expressway programme is scheduled to be substantially completed.
- 2031: That expressway section is scheduled to enter operation and use.
- Before 2035: The remaining components must be completed and synchronized, with the government aiming to finish the entire route within that deadline.
The second quarter approval deadline is especially important because it comes shortly before the planned construction start. Local authorities and the Construction Ministry must complete the detailed investment procedures, while agencies responsible for land, utilities, environmental matters and materials must remove obstacles that could prevent sites from being handed to contractors.
Who will approve and coordinate the work
The Minister of Construction and the chairs of the People's Committees in the seven participating localities must exercise the authority of investment decision makers for their assigned components. They are responsible for organizing the preparation, appraisal and approval of feasibility study reports. A feasibility study sets out the detailed case for a component, including whether its technical proposal and funding arrangements are ready to proceed.
The Construction Ministry is the focal point for implementation. It must keep the component projects consistent with one another, provide technical support and help resolve difficulties involving construction regulations, standards and engineering solutions. It must also urge local governing bodies to meet the required quality and schedule.
The ministry has two further coordination tasks. It must lead the drafting and issuance of rules governing cooperation between the ministry and the other governing bodies, and it must work with those bodies to issue implementation plans for the component projects. These arrangements are intended to give seven local administrations and several national ministries a common way of managing a route that crosses numerous administrative boundaries.
Agencies assigned to govern component projects must also apply the special mechanisms and policies permitted by the National Assembly under Resolution 38/2026/QH16. The government requires strict procedures, economical and efficient use of capital, public transparency, and comprehensive responsibility for quality, progress, synchronization and effectiveness. Its instructions explicitly call for preventing corruption, group interests, waste and losses of state assets.
How funding is meant to keep pace with construction
The Finance Ministry must consolidate proposals from the Construction Ministry and the localities, then report to the government on assigning the public investment plan for 2026 to 2030 to the expressway component projects. It must also report to the competent authorities on prioritizing state budget resources for continued investment in Ring Road 5.
Funding can be coordinated among component projects that use central budget money so that allocations follow implementation progress. Such adjustments must not push spending beyond the preliminary total investment approved by the National Assembly. The arrangement provides room to move resources where work is advancing while retaining the financial ceiling set for the project.
The Finance Ministry must also advise the government on using lawful funding sources within its authority so that sufficient money matches the construction schedule. Its instruction is to prevent stops or temporary suspensions caused by an inability to balance capital. Any funding arrangement must remain compatible with the state budget's capacity in each period and with the national plan for public borrowing and debt repayment.
Provinces can additionally advance local budget money for tasks that belong to the central budget. This applies when central resources have been balanced but have not yet been allocated in time. The central budget must reimburse the locality once the money is arranged. An advance cannot exceed the central budget investment plan already assigned to the project for the multi-year period, minus the annual estimates that have already been provided. In practical terms, a province can keep eligible work moving while waiting for central money, but the advance remains bounded by the approved plan.
Where private investment could fit
Private capital remains under consideration even though the full project is described as public investment. Governing agencies must continue studying and assessing whether individual components should use a partnership between public bodies and private investors, commonly called a public private partnership. Under this approach, a private party participates in financing or delivering infrastructure under an agreed allocation of responsibilities.
The purpose of the review is to select a suitable investment form and attract more resources from outside the state budget. Resolution 406/NQ-CP does not identify which components will use private capital or specify an amount to be raised. Those choices remain part of the preparation and appraisal work for the component projects.
Land, side roads and daily life along the route
Local People's Committees carry the responsibilities closest to households and businesses affected by construction. Besides arranging compensation and resettlement funding, they must tightly manage the land associated with the project. The government has told them to prevent complicated situations during land recovery, compensation, support and resettlement that could affect people's lives.
The parallel roads add another local obligation. Hai Phong, Bac Ninh, Ninh Binh and Hung Yen must prioritize the sections needed when the first expressway programme opens. Their timing matters because a high-speed route through an area does not by itself provide the local connections needed for everyday travel. Side roads preserve those shorter connections and are central to the resolution's requirement for safe and convenient traffic conditions.
For residents near the planned route, the earliest visible effects are therefore likely to come through land procedures, utility relocation, environmental review and side road preparation rather than expressway traffic itself. The resolution places those tasks on named local and national bodies before the September 2027 construction milestone.
The agencies clearing physical and regulatory obstacles
The Ministry of Agriculture and Environment must guide or resolve difficulties within its authority concerning compensation, support and resettlement. Its remit also covers environmental impact assessments, changes in forest land use, construction waste disposal sites and related matters. Where an issue exceeds its authority, the ministry must advise the competent level of government.
The same ministry handles matters involving works within dyke protection areas, riverbanks, riverbeds and irrigation canals under the laws governing dykes and irrigation. These assignments address specific places where a road corridor can meet water management systems or require changes to land and forest use.
The Ministry of National Defence must help local authorities resolve issues involving defence land and the clearance of bombs, mines and explosive objects. It must also urgently relocate technical infrastructure under its management so that construction sites can be handed over on schedule. The Ministry of Public Security has parallel duties for infrastructure it manages, alongside support for security and public order during compensation, resettlement and construction. It must also direct the appraisal of fire prevention and firefighting designs for project works.
Vietnam Electricity is the investor for subprojects relocating electricity installations rated at 110 kilovolts or more. It must ensure that sites are handed over in line with the component project schedules. This gives the power utility a direct role in preparing construction corridors rather than leaving electricity relocation as a separate task without a named project investor.
Materials, power lines and the 2031 opening target
The Ministry of Industry and Trade must work with other ministries, sectors and localities to issue the materials coordination mechanism before September 2027. Its purpose is to prioritize construction materials for the component projects across regional and provincial boundaries. The ministry must also help resolve obstacles in mineral activities serving the project under the laws on geology and minerals and any applicable special policies.
The materials deadline, Vietnam Electricity's relocation duties and the site clearance assignments all feed into the same construction timetable. Feasibility approvals are due by the second quarter of 2027, followed by the planned start in September. The first 116 km then has a substantial completion target in 2030 and an operating target in 2031.
The remaining components have no individual construction start dates in this implementation schedule. Their stated requirement is completion and synchronization with the full project before 2035. For the four localities hosting the initial expressway programme, the nearer test is whether funding, land, materials, utility relocation and local side roads can advance together quickly enough to support the 2031 opening target.
Key Points
- Central budget funding for the main expressway line during 2026 to 2030 is capped at 61.394 trillion dong.
- The allocation covers about 116 km in Hai Phong, Bac Ninh, Ninh Binh and Hung Yen, not local compensation or parallel road costs.
- The full Ring Road 5 project spans about 349 km across seven localities and has preliminary total investment of about 288.268 trillion dong.
- Component approvals are due by the second quarter of 2027, with construction planned for September 2027.
- The first expressway programme is due for substantial completion in 2030 and operation in 2031.
- Local budgets must finance land recovery, compensation, resettlement and side roads, while provinces may advance money for eligible central budget tasks.
- The full route is targeted for completion before 2035, and public private partnerships remain under study for individual components.