Vietnam Moves to Reclassify Data Center Power
Vietnam's Ministry of Industry and Trade is seeking comments on draft amendments to Circular 60/2025/TT-BCT that would apply the manufacturing electricity price to data centers, replacing the current practice of classifying them by purpose of use. The ministry issued the urgent notice on November 19, 2026, asking agencies and organizations to submit feedback before November 25, 2026. The change would resolve a costly dispute over whether data centers should pay business rates or the lower production rates.
Contents
- Vietnam Moves to Reclassify Data Center Power
- What Counts as a Data Center Under the Draft
- Why the Old Rules Became Unworkable
- The Audit Finding That Forced a New Draft
- Viettel and CMC Faced Cost Increases Above 50 Percent
- Power Officials Warn of a Data Center Rush
- Vietnam's Data Center Market Is Small but Growing Fast
- The Power System Is Already Under Strain
- Rethinking the National Power Plan
- What the Change Would Mean and What Is Not Yet Decided
- Key Points
Under current rules, data centers that serve other organizations or individuals pay the business electricity price. Facilities that serve only the operator's own business are billed according to the purpose stated in their existing power purchase agreement. Where a facility uses power for several purposes, the buyer and seller must agree on how to split consumption. That split has proven difficult because data center power systems can serve internal operations and outside customers at the same time.
The draft adds data center operations to the groups covered by manufacturing electricity prices under Article 7 and amends Article 11 to take data centers out of the category of centralized data processing, storage, and management facilities charged at business rates. Offices and customer service points would stay on the business tariff. The ministry says the change would give pricing a uniform legal basis and stop power utilities and enterprises from applying the rules differently.
What Counts as a Data Center Under the Draft
The draft defines a data center as a telecommunications facility made up of buildings, stations, cabling systems, computers, electrical systems, and supporting equipment used to process, store, and manage data for one or more organizations or individuals. Data center operations would join the group eligible for production electricity prices. Other entities that provide centralized data processing, storage, and management services but do not meet that definition would remain on the business tariff.
The distinction matters because electricity powers more than the computers that handle data. A data center's technical systems include the equipment needed to keep those computers and storage systems running. The Ministry of Science and Technology recommended applying production prices to the technical systems, whether they serve the operator's internal needs or outside clients, while charging the business tariff for offices, customer service points, and other commercial activities.
The difference in rates is substantial. From early November, production rates ranged from 1,101 to 3,586 dong per kilowatt hour, while business rates ranged from 1,577 to 5,313 dong, depending on voltage level and time of use. The figures exclude value added tax. At the voltage level above 1 kilovolt and up to 35 kilovolts, the normal hour production rate was 1,814 dong per kilowatt hour, 1,015 dong, or nearly 36 percent, below the business rate. At off peak hours, from midnight to 6 a.m., and peak hours, from 5:30 p.m. to 10:30 p.m., production rates were 26 to 32 percent lower than business rates. A lower tariff could reduce operating bills for data centers currently charged at business rates.
Why the Old Rules Became Unworkable
Vietnam's data center industry was once small enough that facilities were generally charged industrial electricity rates under Circular 16/2014. As the industry expanded and the Telecommunications Law 2023 introduced new provisions, the ministry revised the pricing framework through Circular 60/2025/TT-BCT. That circular placed facilities providing data services to other organizations or individuals under business rates. Facilities serving only their own company were billed according to the purpose recorded in their existing electricity purchase contract. For a facility using power for several purposes, the buyer and supplier had to agree on the share for each activity.
In practice, many modern facilities simultaneously support internal business operations and provide services to third parties. Their technical systems are shared, making it difficult for operators and electricity suppliers to distinguish consumption by purpose. The ministry said it received numerous recommendations about electricity pricing for data centers during the implementation of Circular 60. The Ministry of Science and Technology proposed applying the same electricity tariff to all data center services, regardless of whether they serve the operator or outside customers, arguing that a data center's technical systems directly create and maintain its capacity to deliver services, which makes them equivalent to manufacturing.
The ministry followed that recommendation with Official Letter 2818 on April 22, 2026. The letter provided guidance that industrial electricity tariffs should apply to the technical systems of data centers when electricity buyers and suppliers cannot agree on how consumption should be allocated between different purposes. The guidance did not settle the matter.
The Audit Finding That Forced a New Draft
The State Audit Office of Vietnam later examined Vietnam Electricity, the state utility known as EVN, and questioned the legal validity of Official Letter 2818. The audit authority noted that the letter was an administrative document addressing specific circumstances and could not supersede the provisions of Circular 60. It warned that applying pricing guidance inconsistent with the circular could create unequal treatment among businesses and undermine the effectiveness of existing regulations.
The Ministry of Industry and Trade therefore considers amendments to Circular 60 necessary to establish a clear legal basis and ensure consistent electricity pricing for data centers nationwide. The draft would formally incorporate the relevant pricing provisions into the circular, rather than relying on a letter that the audit office found legally weaker than the circular. The ministry says this would keep power supply to data centers continuous and stable.
The regulatory path has spanned several years and several documents. A short timeline shows how the rules changed:
- 2014: Circular 16/2014/TT-BCT sets industrial electricity rates for many large power users, including data facilities before they became a distinct service category.
- 2023: The Telecommunications Law introduces new provisions for data and telecommunications services.
- 2025: Circular 60/2025/TT-BCT revises retail electricity pricing and places data centers serving outside customers on business rates.
- April 9, 2026: The Ministry of Science and Technology asks the Ministry of Industry and Trade for clearer guidance on electricity pricing for data centers.
- April 22, 2026: The Ministry of Industry and Trade issues Official Letter 2818, allowing industrial tariffs for data center technical systems when buyers and suppliers cannot agree on consumption shares.
- November 19, 2026: The ministry issues an urgent notice seeking comments on draft amendments to Circular 60 by November 25, 2026.
- November 25, 2026: Deadline for comments on the draft amendments.
Viettel and CMC Faced Cost Increases Above 50 Percent
The regulatory dispute has already had financial consequences for major Vietnamese technology companies. Viettel and CMC submitted petitions to the Ministry of Industry and Trade after their data centers in Ho Chi Minh City were charged commercial electricity rates, while similar facilities in other localities continued to receive industrial tariffs. According to the companies, switching to commercial electricity pricing increased their power costs by more than 50 percent.
The two businesses were also asked to pay approximately VND9.62 billion, around $363,000, in additional electricity charges and faced the possibility of having their electricity supplies suspended. The dispute stemmed from differing interpretations of the ministry's guidance and the State Audit Office's findings. While the Ministry of Industry and Trade had instructed electricity suppliers to apply industrial tariffs to data center technical systems under certain circumstances, the State Audit Office maintained that such guidance could not override Circular 60.
Faced with conflicting interpretations, Ho Chi Minh City Power Corporation, known as EVNHCMC, requested that the Ministry of Industry and Trade and EVN issue consistent instructions to minimize legal risks and prevent disruptions to data center operations. The Ministry of Science and Technology sent three separate written requests urging the Ministry of Industry and Trade to direct EVN to implement the earlier guidance consistently. The latest proposal seeks to resolve these differences by formally incorporating the pricing provisions into Circular 60.
Power Officials Warn of a Data Center Rush
The tariff change comes as energy officials warn that data center investment is outpacing the country's power system. At a forum on energy for sustainable development organized by the Vietnam Chamber of Commerce and Industry on November 19, Bui Quoc Hoan, deputy general director of Southern Power Corporation, a subsidiary of EVN known as EVNSPC, said electricity connection requests for data centers in EVNSPC's service area had surged to 4,000 MVA in just a few months. The largest data center project currently under development in Vietnam has a capacity of 140 MVA.
EVNSPC manages power distribution infrastructure across eight southern provinces and cities. Hoan argued that the registered pipeline far exceeds the capacity required to serve the domestic digital economy. Because Vietnam's state regulated, relatively low electricity prices make local data center leasing rates considerably cheaper than those in Singapore and Taiwan, projects built strictly for foreign tenants risk becoming a backdoor export of cheap domestic energy while placing severe strain on national grid security. He called for scrutiny of this emerging electricity intensive sector.
There needs to be a serious and careful assessment of a new type of load, data centers.
Hoan pointed to neighboring Southeast Asian nations that have recently moved to curb speculative power hoarding. Thailand has issued new regulations tying project approvals to tangible domestic economic contributions, implemented dedicated electricity tariffs for data centers, and mandated security deposits to prevent developers from locking up grid quotas without building. Malaysia requires data centers to independently secure at least 30 percent of their electricity consumption.
The lesson from Malaysia shows that the country has required data centers to self ensure 30 percent of their electricity consumption.
Vietnam's Data Center Market Is Small but Growing Fast
Vietnam's data center supply remains less than 10 percent of that in Thailand and Malaysia, according to Cushman & Wakefield. Ho Chi Minh City currently hosts 33 MW across 14 facilities run by nine providers, while 68 MW of new supply has been announced. The market is set to grow from a capacity of 310 MW in 2025 to 580 MW in 2031, according to Mordor Intelligence. That firm said enterprise spending on digital transformation, data localization rules, and the removal of caps on foreign ownership are speeding up builds in Hanoi and Ho Chi Minh City.
A report on data centers and their applications in the financial sector recently released by VietinBank Securities estimated that Vietnam currently has approximately 148 MW of operational data center capacity, another 79 MW under construction, and 874 MW in the development pipeline. Under its base case scenario, VBSE forecasts that operational data center capacity in Vietnam could reach 600 to 900 MW by 2030, requiring an estimated $4 billion to $7 billion in construction investment, excluding information technology equipment.
Nguyen Ngoc Hung from the Energy Institute said current data center capacity remains below 200 MW. The scale of projects registered by businesses and local authorities could be considerably larger if proposed investments materialize. Local authorities have registered approximately 68.6 GW of additional electricity demand by 2035, including around 44 GW by 2030 and another 24 GW from 2031 to 2035. Data centers require large amounts of power around the clock and highly reliable supplies, and their geographical concentration means that a project with hundreds of megawatts of demand could place considerable pressure on the local grid.
The Power System Is Already Under Strain
Pressure on Vietnam's electricity supply is intensifying. Huynh Anh Tuyen, deputy head of the Ministry of Industry and Trade's representative office in the central and southern regions, said the pressure on the energy system is growing. Industrial hubs in the southeast and agricultural processing centers in the Mekong Delta keep demand at peak levels. The requirement is no longer just enough electricity, but clean electricity.
Nguyen Duc Hien, deputy head of the Central Commission for Policy and Strategy, noted that to sustain double digit GDP growth between 2026 and 2030, commercial electricity output should expand by 11 to 12 percent annually. Generation growth averaged 10.3 percent in 2026, below the target. The national power system's reserve margin is narrowing rapidly as operations rely heavily on existing generation sources. The Ministry of Industry and Trade warned that without major policy breakthroughs, Vietnam may face a power deficit of 4,300 MW in 2027, ballooning to nearly 14,000 MW by 2030, equivalent to about 61.2 billion kWh.
Pressure to ensure energy security to meet domestic production demand is rising very fast as the scale of the economy expands.
Hien called for removing financial and regulatory obstacles facing LNG fired power and offshore wind projects, particularly those involving power purchase agreements, pricing frameworks, contracted output ratios, and pilot mechanisms for large scale developments. Other priorities include resolving legal obstacles affecting existing renewable energy projects, issuing clearer guidelines for private sector participation in 500 kV and 220 kV transmission infrastructure, and completing the competitive electricity market framework. He also highlighted the need to expand direct power purchase agreements, mobilize green financing, encourage rooftop solar development, and strengthen supporting industries to reduce reliance on imported equipment and materials.
Rethinking the National Power Plan
Vietnam is reassessing its national power development plan to address rapidly changing electricity demand and mounting risks to power project implementation. The review of the adjusted eighth Power Development Plan, or PDP8, comes as electric vehicles, artificial intelligence, data centers, and semiconductor manufacturing create new sources of electricity demand. Deputy Minister of Industry and Trade Truong Thanh Hoai stressed the need to improve plan revisions to ensure long term stability in the power sector, urging greater focus on the accuracy of input data and demand forecasts and thorough assessment of delays affecting major power projects. The ministry is also revising the Electricity Law to address implementation bottlenecks and strengthen the feasibility of the power plan.
Nguyen Ngoc Hung from the Energy Institute said Vietnam had more than 200,000 electric cars and approximately 2.2 million electric motorbikes in 2025, with combined electricity consumption estimated at around 750 million kWh. Electricity consumption at charging stations reached approximately 600 million kWh last year.
The adjusted PDP8, approved under Prime Ministerial Decision 768/QD-TTg from April 2025, sets a target of up to 236,363 MW in total installed generation capacity by 2030 to serve domestic demand, with maximum system load projected at 99,934 MW. Nguyen Huy Hoach, from the scientific council of the Vietnam Energy Review, cautioned against assuming that all planned generation capacity would be completed and become operational on schedule. For LNG fired power, project feasibility depends on construction progress as well as on imported fuel prices, port and storage infrastructure, fuel supply security, power purchase agreements, and the commercial mechanisms governing electricity generation. Offshore wind has significant potential but involves lengthy development cycles, requiring marine surveys, sea space planning, investment capital, grid connections, and appropriate electricity pricing mechanisms.
Hoach identified three potential gaps between planning and actual requirements: delays in identifying new electricity demand, geographical mismatches between generation and consumption, and the lengthy investment and construction cycles for major energy infrastructure. He said the review should move away from relying on a single electricity demand forecast toward multiple scenarios combining different levels of consumption growth with realistic power project implementation schedules. A baseline scenario could reflect updated demand data, while a high growth scenario should account for faster than expected expansion of data centers, semiconductor manufacturing, advanced technology industrial parks, electric transport, and major infrastructure projects. Each demand scenario should also be matched with alternative generation schedules. If LNG projects are delayed by two or three years, for example, the system must identify replacement sources and determine when additional capacity and transmission infrastructure are needed.
Pham Viet Thuan, head of the Institute of Natural Resources and Environmental Economics in Ho Chi Minh City, recommended restructuring Vietnam's power generation mix to reduce dependence on coal and raise the share of clean energy to 26.1 percent by 2030. The government should accelerate investment in energy storage technologies to store renewable electricity, stabilize the power system, and reduce generation costs. He also noted that data centers of 200 MW to 500 MW consume enormous amounts of electricity and require continuous supply.
Without solving the problem of generation infrastructure, storage systems and grid reliability, the economy will struggle to realize digital transformation and sustainable development goals.
What the Change Would Mean and What Is Not Yet Decided
If adopted, the amendments would establish a clearer distinction between qualifying data center operations and other commercial data services, providing a more consistent framework for electricity billing. For operators such as Viettel and CMC, greater regulatory clarity could help reduce uncertainty over operating costs and electricity supply arrangements. A lower tariff could reduce operating bills for data centers currently charged at business rates and establish a clearer rule for facilities whose servers, storage equipment, electrical systems, and supporting equipment serve several customers at once.
The proposal also fits a broader debate about who should pay for the power system that supports Vietnam's digital economy. Data centers that serve domestic needs and contribute to growth are reasonable, Hoan said, while projects developed only to lease infrastructure to foreign partners risk exporting cheap energy under the cover of digital transformation. The draft would keep offices and customer service points on the business tariff, so the manufacturing rate would not apply to every part of a data center business.
No date has been given for final adoption of the amendments. The ministry's comment period closes on November 25, 2026. The State Audit Office's findings remain part of the record that the ministry is trying to address. The Ministry of Industry and Trade is also reviewing the PDP8 and the Electricity Law, with decisions expected on demand forecasts, generation schedules, and transmission investments. The next signals for data center operators will come from the ministry's response to comments on the circular and from any new guidance on power purchase agreements and grid connection.
Key Points
- Vietnam's Ministry of Industry and Trade proposes applying manufacturing electricity prices to data centers under draft amendments to Circular 60/2025/TT-BCT.
- The ministry issued an urgent notice on November 19, 2026, asking for comments before November 25, 2026.
- Current rules put data centers that serve outside customers on business rates, while facilities serving only their operator are billed by the purpose in their power purchase agreement.
- The split has been hard to apply because data centers often serve internal operations and outside customers at the same time.
- The State Audit Office of Vietnam found that Official Letter 2818, issued on April 22, 2026, could not override Circular 60, prompting the ministry to seek a formal amendment.
- Viettel and CMC said commercial rates raised their power costs by more than 50 percent and were asked to pay about VND9.62 billion, around $363,000, in additional charges.
- EVNSPC's Bui Quoc Hoan said data center connection requests in its area reached 4,000 MVA in a few months, while Vietnam's largest project under development is 140 MVA.
- Vietnam's data center supply is less than 10 percent of Thailand's and Malaysia's, with Ho Chi Minh City hosting 33 MW across 14 facilities.
- The Ministry of Industry and Trade warned of a 4,300 MW power deficit in 2027 growing to nearly 14,000 MW by 2030.
- VietinBank Securities estimates 148 MW of operational data center capacity, 79 MW under construction, and 874 MW in the pipeline, with $4 billion to $7 billion needed by 2030.
- The adjusted PDP8 targets up to 236,363 MW of installed generation capacity by 2030, with local authorities registering about 68.6 GW of additional demand by 2035.