Central Bank Filings Tie Alice Huang Network to US$301 Million of AI Hardware in Shanghai

10 Min Read
Central Bank Filings Tie Alice Huang Network to US$301 Million of AI Hardware in Shanghai

Credit Registry Lists 764 Servers and Modules

Filings held in a credit registry run by China's central bank list up to 764 AI servers and modules with a declared value of US$270 million, plus US$31 million of networking equipment used to link them into large computing clusters. The two figures add up to US$301 million of hardware that businesses tied to Alice Huang pledged to raise loans and other financing.

Contents
  1. Credit Registry Lists 764 Servers and Modules
  2. Century Litong and 512 Servers Under Lease
  3. Why Borrow Against Servers Instead of Buying Them
  4. The Project Tencent Started, Then Saw Renamed
  5. Tencent Denies Building the Facility
  6. Sisters, Husbands and Company Records
  7. A Second Site in Wuhu and a US$70 Million Loan
  8. An H800 Delivery and a Place on the Blacklist
  9. What Is Not Known
  10. Key Points

Alice Huang formerly controlled Megaspeed, a major overseas buyer of Nvidia processors. Her relationship with Jensen Huang, who stepped down as Nvidia's chief executive this month and returned to the post 11 days later, has sharpened scrutiny of how the chipmaker's products reach China.

Most of the hardware is listed at a large data centre in Shanghai's Songjiang district, built as part of a project that began with a cooperation agreement between Tencent and the district government in 2020. The filings show what lenders were told the machines were worth and where they sat, not who bought them or how they crossed a border.

On Monday the US Commerce Department added Megaspeed to its trade blacklist, a roster known as the Entity List that requires American suppliers to obtain a licence before selling to a listed company. The step came as US authorities examined whether Megaspeed helped Chinese customers obtain Nvidia chips that export rules restrict. Megaspeed, which is registered in Singapore, denies wrongdoing and says Alice Huang left the company in August 2025.

Sellers in the United States now need a licence to supply Megaspeed, and licences for controlled processors are granted only in exceptional cases. The company had built its business on buying Nvidia parts in volume for customers outside China, a trade that put it among the largest overseas purchasers of the chips.

Advertisement

Century Litong and 512 Servers Under Lease

Century Litong, a cloud partner in Nvidia's preferred partner programme that rents servers to customers needing heavy computing capacity, is the busiest borrower in the documents. Five leasing arrangements between May and December 2024 cover up to 512 servers with a declared value of 1.42 billion yuan.

Four of those arrangements place the equipment at the Yangtze River Delta AI supercomputing centre in Shanghai, part of a data centre complex whose infrastructure developer was Shanghai Longrui. One deal describes 128 servers at the centre, each carrying eight graphics processors for 1,024 chips in total, with computing power stated as 989 petaflops and a declared value of up to US$450,000 a server. A petaflop is a thousand trillion calculations a second, so 989 petaflops describes close to 989 quadrillion calculations a second across that cluster.

A second transaction covered 128 servers worth US$57 million, financed by an arm of AVIC, an aviation and defence group owned by the Chinese state, and leased to Century Litong. A separate inventory listed at the Shanghai site shows more than 10,000 Nvidia ConnectX-7 networking cards and 730 BlueField-3 units, the components that tie thousands of machines together for AI work.

Lettall Electronic, a manufacturer, invested in Century Litong in 2023 and owned it outright by the middle of 2024. Its disclosures show guarantees it provided for Century Litong's equipment leasing agreements with financial institutions, and a 2023 disclosure from Jiangsu Lettall Electronic named the Yangtze River Delta centre as a site for Century Litong's server rental business.

Advertisement

Why Borrow Against Servers Instead of Buying Them

A machine holding eight processors, plus the networking to connect it, can cost hundreds of thousands of dollars, and export controls have made such equipment harder to source in China. Pledging servers as collateral lets a company put them to work without paying the full purchase price in advance, while a leasing firm or a bank holds a claim on the hardware until the debt is cleared.

Chinese lenders log these pledges in the central bank registry so that other banks can see what has already been committed. This is why the filings reveal the physical location and stated value of machines even when the buyer, the owner and the operator are three different companies.

The dollar figures reflect the value of assets covered by financing arrangements, not necessarily fresh spending or separate purchases, so the same machine can appear in more than one deal.

Advertisement

The Project Tencent Started, Then Saw Renamed

Tencent and the Songjiang district government signed their strategic cooperation agreement on 31 March 2020 to build an AI supercomputing centre with an industrial park around it. Early investment was put at 45 billion yuan. Land was acquired on 27 May 2020, a construction permit followed three days later and work began on 6 June. The first plan covered 353,920 square metres; later figures put the built area above 500,000 square metres.

Century Huatong, a gaming company that counts Tencent as a shareholder of roughly 10%, announced on 15 June 2020 that it would buy 10% of Shanghai Longrui and inject 3.1 billion yuan, alongside a plan to raise 5.7 billion yuan in convertible bonds. Longrui became its subsidiary that year. In 2021 Century Huatong agreed to sell 50.10% of Longrui to GLP and affiliates for 4 billion yuan, with the buyer taking on 2 billion yuan of acquisition debt. The site holds the largest electricity connection of any data centre in Shanghai, and its first two power lines were energised in June 2021.

In July 2026 the Songjiang district data bureau adopted a change of name in a report on public consultation over a plan for 2026 to 2030 that combines 6G, AI, satellite internet and space computing. The Tencent Yangtze River Delta AI advanced computing centre became the Longrui Yangtze River Delta AI advanced computing centre. A release issued around the same time said 12,000 cabinets were built and in service, more than 48,000 GPUs had been deployed, and the site carried the main training and inference work for Tencent's Hunyuan and Yuanbao models. At completion the site is planned to hold 16 buildings, about 40,000 cabinets and 800,000 servers.

Advertisement

Tencent Denies Building the Facility

A Tencent spokesperson rejected any role in the project as described in the filings and said the company's name had been used without permission.

Tencent did not develop or co-develop the data centre facility in question.

The spokesperson said Tencent has never owned or operated the Yangtze River Delta data centre project and that its name and trademarks were used without authorisation. Tencent also denied any commercial relationship with Megaspeed or its subsidiaries. The records do not establish that Tencent bought, rented or operated the servers identified in the filings.

Advertisement

Sisters, Husbands and Company Records

Corporate records connect Century Litong, Century Longteng and Century Huatong to Alice Huang's sister, Huang Yu, and to Kang Wei, an investment executive who is Alice Huang's husband. Kang was named Century Longteng's executive director in a 2022 government announcement and has been identified as president of the Shanghai data centre.

Century Litong was set up in 2023 as a subsidiary of Shanghai Century Longteng. Longteng is now wholly controlled by Century Huatong, after a Shanghai state investment fund and an investment company linked to Huang Yu and Kang held shares in it earlier. Century Huatong also owns 70% of a company where Alice Huang once served as a director, and holds a stake in the gaming firm 7Road Holdings, whose former overseas subsidiary was renamed Megaspeed in 2023.

A Second Site in Wuhu and a US$70 Million Loan

The same network built a large data centre in Wuhu, about 300km (186 miles) inland from Shanghai. Wuhu Century Longteng, majority owned by Huang Yu through investment vehicles until early 2026, pledged another 252 AI computing modules to Ping An Bank as collateral for a US$70 million loan in April 2026. The documents did not say where those modules are.

Advertisement

An H800 Delivery and a Place on the Blacklist

Strider Technologies, an intelligence firm based in the United States, concluded in an investigation that Century Litong delivered a batch of servers carrying Nvidia's H800 chip to the Shanghai centre in October 2023, the same month a US export ban took effect. Whether that shipment complied with the rules is not clear.

Nvidia designed the H800 for the Chinese market in 2022 after earlier restrictions, trimming the links between chips to keep the part outside the controls. The October 2023 rules covered that design as well, closing the gap. The restrictions mean Chinese buyers cannot simply order the most advanced processors from American suppliers, which is why access to machines already inside the country, and the loans secured on them, matter so much to AI developers.

  • March 2020: Tencent and the Songjiang district sign their cooperation agreement.
  • June 2020: Century Huatong buys 10% of Shanghai Longrui and injects 3.1 billion yuan.
  • 2023: Century Litong is established under Shanghai Century Longteng.
  • October 2023: servers with H800 chips are delivered to the Shanghai centre in the month a US ban takes effect.
  • May to December 2024: five lease arrangements cover up to 512 servers valued at 1.42 billion yuan.
  • August 2025: Alice Huang leaves Megaspeed.
  • April 2026: Wuhu Century Longteng pledges 252 modules for a US$70 million loan from Ping An Bank.
  • July 2026: the Songjiang data bureau adopts the Longrui name for the project.
  • November 2026: Jensen Huang steps down and returns after 11 days; the Commerce Department adds Megaspeed to its blacklist.
Advertisement

What Is Not Known

The filings do not establish that the servers held chips barred from export to China, and they do not show how or when the equipment entered the country. They carry no location for the Wuhu modules and no timetable for any review of Megaspeed's listing.

Nvidia, Century Litong, Century Huatong, Shanghai Longrui, Lettall and AVIC did not respond to requests for comment. The Songjiang district government did not reply to a request sent by fax. Alice Huang, Huang Yu and Kang Wei could not be reached.

Key Points

  • Central bank filings list up to 764 AI servers and modules worth US$270 million, plus US$31 million of networking equipment, for a total of US$301 million.
  • Most of the hardware is listed at a Shanghai data centre built under a 2020 Tencent partnership with the Songjiang district government.
  • Century Litong took out five leases from May to December 2024 covering up to 512 servers valued at 1.42 billion yuan.
  • One deal covered 128 servers financed by an arm of AVIC and leased to Century Litong; another described 1,024 chips with 989 petaflops of computing power.
  • Tencent says it did not develop or operate the facility and that its name was used without authorisation.
  • Records link Century Litong and Century Longteng to Huang Yu, Alice Huang's sister, and to her husband Kang Wei.
  • Megaspeed was added to the US trade blacklist on Monday; the company denies wrongdoing and says Alice Huang left in August 2025.
  • The filings do not show that the servers held restricted chips or how the equipment reached China.